Preparation of Lviv Airport to EURO’2012 04 February 2009
Current outlook of International Airport “Lviv” Сonstructed in 1950th Capacity 300 PAX/H Runway 2500 m
Host countries of EURO – 2012. Lviv has Strategic position The longest Distance to the farest Host City is 1200 km Gdansk POLAND Lviv UKRAINE Donetsk
Lviv Airport location within City 1 Airport 2 City Centre 4 2 5 km (15-20 min) Stadium 3 7 km (20-30 min) Railway station 4 1 12 km (30 min) 3
Project Organization Project Owner - Ministry of Transport Client – Lviv International Airport Sub -project Project Architect General Contractor Consultant
Project Scope of Airport reconstruction 5 3 4 2 2 1.2 1.1 2 510 m 2 3 200 m • 1. Reconstruction, extension of the runway: • 1.1 Extension of the runway. • 1.2 Reconstruction of the runway (strengthening of the existing pavement) • Reconstruction of the apron • Reconstruction of the existing air terminal • Construction of the new passenger terminal • Existing hotel 1 1.1 1.2 2 3 4 5
Master plan of Airport and surrounding Territory 3 5 3 4 2 5 1 • Existing Terminal • NewTerminal • Hotels • Parking • Service Centers
Time Schedule for Reconstruction of Runway and Apron Progress End 2011 Now Before 3 March 2009 4 March 2009 Reconstruction END Reconstruction START Design is finished and approved Selection of General contractor
Key Data for new Terminal • New Terminal Building (34,000 m2) category ‘C’, in compliance with requirements of ICAO and IATA • Capacity - 1000 passengers per hour
New Terminal building Progress End 2010 Now 27 March 2009 4 May 2009 Building END Building START New terminal design in progress Design will be completed
Financing (current status) • Reconstruction of Runway - 27,2 mln.Euro (State Budget) • Reconstruction of Apron - 16,9 mln. Euro (State Budget) • Reconstruction of existing terminal - 12,6 mln. Euro (State Budget) • Construction of New terminal – 90,0 mln. Euro (Investor )
Reserve Airports Lutsk Розміщення резервних аеропортів 152 кm Lviv 135 кm Ivano-Frankivsk