1 / 29

EE 369 POWER SYSTEM ANALYSIS

EE 369 POWER SYSTEM ANALYSIS. Lecture 17 Optimal Power Flow, LMPs Tom Overbye and Ross Baldick. Announcements. Read Chapter 7. Homework 11 is 6.43, 6.48, 6.59, 6.61, 12.19, 12.22; due November 21. Homework 12 is 12.20, 12.24, 12.26, 12.28, 12.29; due Tuesday, November 26.

Thomas
Télécharger la présentation

EE 369 POWER SYSTEM ANALYSIS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. EE 369POWER SYSTEM ANALYSIS Lecture 17 Optimal Power Flow, LMPs Tom Overbye and Ross Baldick

  2. Announcements • Read Chapter 7. • Homework 11 is 6.43, 6.48, 6.59, 6.61, 12.19, 12.22; due November 21. • Homework 12 is 12.20, 12.24, 12.26, 12.28, 12.29; due Tuesday, November 26. • Homework 13 is 12.21, 12.25, 12.27, 7.1, 7.3, 7.4, 7.5, 7.6, 7.9, 7.12, 7.16; due Thursday, December 5.

  3. Electricity Markets • Over last ten years electricity markets have moved from bilateral contracts between utilities to also include spot markets (day ahead and real-time). • OPF is used as basis for real-time pricing in major US electricity markets such as MISO, PJM, CA, and ERCOT (from December 2010).

  4. Electricity Markets • Electricity (MWh) is now being treated as a commodity (like corn, coffee, natural gas) with the size of the market transmission system dependent. • Tools of commodity trading have been widely adopted (options, forwards, hedges, swaps).

  5. Electricity Futures Example Source: Wall Street Journal Online, 10/30/08

  6. “Ideal” Power Market • Ideal power market is analogous to a lake. Generators supply energy to lake and loads remove energy. • Ideal power market has no transmission constraints • Single marginal cost associated with enforcing constraint that supply = demand • buy from the least cost unit that is not at a limit • this price is the marginal cost. • This solution is identical to the economic dispatch problem solution.

  7. Two Bus ED Example

  8. Market Marginal (Incremental) Cost Below are some graphs associated with this two bus system. The graph on left shows the marginal cost for each of the generators. The graph on the right shows the system supply curve, assuming the system is optimally dispatched. Current generator operating point

  9. Real Power Markets • Different operating regions impose constraints – may limit ability to achieve economic dispatch “globally.” • Transmission system imposes constraints on the market: • Marginal costs differ at different buses. • Optimal dispatch solution requires solution by an optimal power flow • Charging for energy based on marginal costs at different buses is called “locational marginal pricing” (LMP) or “nodal” pricing.

  10. Pricing Electricity • LMP indicates the additional cost to supply an additional amount of electricity to bus. • Some electric markets price wholesale energy at LMP: • ERCOT began this in December 2010. • In there were no transmission limitations then the LMPs would be the same at all buses: • Equal to value of lambda from economic dispatch. • Transmission constraints result in differing LMPs at buses. • Determination of LMPs requires the solution of an “Optimal Power Flow” (OPF).

  11. Optimal Power Flow (OPF) • OPF functionally combines the power flow with economic dispatch • Minimize cost function, such as operating cost, taking into account realistic equality and inequality constraints • Equality constraints: • bus real and reactive power balance • generator voltage setpoints • area MW interchange

  12. OPF, cont’d • Inequality constraints: • transmission line/transformer/interface flow limits • generator MW limits • generator reactive power capability curves • bus voltage magnitudes (not yet implemented in Simulator OPF) • Available Controls: • generator MW outputs • transformer taps and phase angles

  13. OPF Solution Methods • Non-linear approach using Newton’s method: • handles marginal losses well, but is relatively slow and has problems determining binding constraints • Linear Programming (LP): • fast and efficient in determining binding constraints, but can have difficulty with marginal losses. • used in PowerWorld Simulator

  14. LP OPF Solution Method • Solution iterates between: • solving a full ac power flow solution • enforces real/reactive power balance at each bus • enforces generator reactive limits • system controls are assumed fixed • takes into account non-linearities • solving an LP • changes system controls to enforce linearized constraints while minimizing cost

  15. Two Bus with Unconstrained Line With no overloads the OPF matches the economic dispatch Transmission line is not overloaded Marginal cost of supplying power to each bus (locational marginal costs) This would be price paid by load and paid to the generators.

  16. Two Bus with Constrained Line With the line loaded to its limit, additional load at Bus A must be supplied locally, causing the marginal costs to diverge. Similarly, prices paid by load and paid to generators will differ bus by bus.

  17. Three Bus (B3) Example • Consider a three bus case (bus 1 is system slack), with all buses connected through 0.1 pu reactance lines, each with a 100 MVA limit. • Let the generator marginal costs be: • Bus 1: 10 $ / MWhr; Range = 0 to 400 MW, • Bus 2: 12 $ / MWhr; Range = 0 to 400 MW, • Bus 3: 20 $ / MWhr; Range = 0 to 400 MW, • Assume a single 180 MW load at bus 2.

  18. B3 with Line Limits NOT Enforced Line from Bus 1 to Bus 3 is over- loaded; all buses have same marginal cost (but not allowed to dispatch to overload line!)

  19. B3 with Line Limits Enforced LP OPF redispatches to remove violation. Bus marginal costs are now different. Prices will be different at each bus.

  20. Verify Bus 3 Marginal Cost One additional MW of load at bus 3 raised total cost by 14 $/hr, as G2 went up by 2 MW and G1 went down by 1MW.

  21. Why is bus 3 LMP = $14 /MWh ? • All lines have equal impedance. Power flow in a simple network distributes inversely to impedance of path. • For bus 1 to supply 1 MW to bus 3, 2/3 MW would take direct path from 1 to 3, while 1/3 MW would “loop around” from 1 to 2 to 3. • Likewise, for bus 2 to supply 1 MW to bus 3, 2/3MW would go from 2 to 3, while 1/3 MW would go from 2 to 1to 3.

  22. Why is bus 3 LMP $ 14 / MWh, cont’d • With the line from 1 to 3 limited, no additional power flows are allowed on it. • To supply 1 more MW to bus 3 we need: • Extra production of 1MW: Pg1 + Pg2 = 1 MW • No more flow on line 1 to 3: 2/3 Pg1 + 1/3 Pg2 = 0; • Solving requires we increase Pg2 by 2 MW and decrease Pg1 by 1 MW – for a net increase of $14/h for the 1 MW increase. • That is, the marginal cost of delivering power to bus 3 is $14/MWh.

  23. Both lines into Bus 3 Congested For bus 3 loads above 200 MW, the load must be supplied locally. Then what if the bus 3 generator breaker opens?

  24. Typical Electricity Markets • Electricity markets trade various commodities, with MWh being the most important. • A typical market has two settlement periods: day ahead and real-time: • Day Ahead: Generators (and possibly loads) submit offers for the next day (offer roughly represents marginal costs); OPF is used to determine who gets dispatched based upon forecasted conditions. Results are “financially” binding: either generate or pay for someone else. • Real-time: Modifies the conditions from the day ahead market based upon real-time conditions.

  25. Payment • Generators are not paid their offer, rather they are paid the LMP at their bus, while the loads pay the LMP: • In most systems, loads are charged based on a zonal weighted average of LMPs. • At the residential/small commercial level the LMP costs are usually not passed on directly to the end consumer. Rather, these consumers typically pay a fixed rate that reflects time average of LMPs. • LMPs differ across the system due to transmission system “congestion.”

  26. LMPs at 8:55 AM on one day in Midwest. Source: www.midwestmarket.org

  27. LMPs at 9:30 AM on same day

  28. MISO LMP Contours – 10/30/08

  29. Limiting Carbon Dioxide Emissions • There is growing concern about the need to limit carbon dioxide emissions. • The two main approaches are 1) a carbon tax, or 2) a cap-and-trade system (emissions trading) • The tax approach involves setting a price and emitter of CO2 pays based upon how much CO2 is emitted. • A cap-and-trade system limits emissions by requiring permits (allowances) to emit CO2. The government sets the number of allowances, allocates them initially, and then private markets set their prices and allow trade.

More Related