An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. TitleConsult 21Mike Reed - Openreach Name 21st February 2006

  2. Forward looking statements – Caution advised • Certain statements in this presentation are forward-looking and are made in reliance on the safe harbour provisions of the US Private Securities Litigation Reform Act of 1995. These statements include, without limitation, those concerning: BT's plans for transformation of its networks; benefits to customers of the 21CN programme; key milestones and expected timetable for delivery of 21CN; and the benefits in relation to, for example interconnect, convergence and broadband. • Although BT believes that the expectations reflected in these forward-looking statements are reasonable, it can give no assurance that these expectations will prove to have been correct. Because these statements involve risks and uncertainties, actual outcomes may differ materially from those expressed or implied by these forward-looking statements. • Factors that could cause differences between actual outcomes and those implied by the forward-looking statements include, but are not limited to: material adverse changes in economic and financial markets conditions in the markets served by BT; supplier arrangements; future regulatory actions and conditions in BT’s operating areas; technological innovations; developments in the convergence of technologies and the anticipated benefits and advantages of new technologies, products and services, including broadband, not being realised. Consult 21- Information is subject to change and is for discussion purposes only. Dates and timescales are those anticipated and maybe subject to change.

  3. Ongoing Actions LLU/11/2Space & Power (list of effected exchanges) • Although not appropriate to Consult 21 but as part of its implementation of section 7 of the Undertakings published on 22nd September 2005, BT has created an ‘Estimated Space Availability’ list on the LLU Controlled Website:- http://www.btinterconnect.com/llu/lluindex.htm • Customers may use this to record interest proactively by advising BT of their future requirements using the spreadsheet, an extract of which is shown below. Consult 21- Information is subject to change and is for discussion purposes only. Dates and timescales are those anticipated and maybe subject to change.

  4. Ongoing Actions LLU/11/4Space & Power - SNAP Clarification (Single Network Accommodation Process) Again although not sure why this issue has been raised at the Consult21 forum but in an effort to clarify the existing process the following still stands:- • BTW’s position is to ensure that all customers are 100% satisfied with the way that BTW deals with their LLU or Co- location customer orders. • LLU orders and MSAN - “orders are given exactly the same priority and the same criteria applies to both” this being:- • 1st order in, 1st order out and all are time & date stamped on receipt • There will be no queue jumping and currently no plans to change this process • CPs should contact BT if at all unhappy with response on Space or Power at any location to arrange a site visit. Consult 21- Information is subject to change and is for discussion purposes only. Dates and timescales are those anticipated and maybe subject to change.

  5. Ongoing Actions LLU/11/7 - Activity Freeze pre and post Migration • The Transfer Engineering is owned by BTWS and as explained at the last forum an activity freeze pre migration is currently planned to be 12 hours at each site with a migration test post migration then the freeze lifts providing the platform is stable. • All communications will be made to CP’s from the TE Migration Control Centre this will include the Go or No Go decision and details about the freeze. • All order activities will cease whilst the freeze is on however unless unforeseen circumstances dictate, LLUO’s should still be able to access their equipment. LLU/11/8 - Migration and all Broadband products • The Migration plan is owned by 21CN Team but in terms of equivalence there is no change to the current position for LLUO’s in terms of Space, Power Arrangements, Products & Connectivity to the MDF via Tie Cables. • The only caveat to this is that there is a natural desire is to avoid variable solutions and if at all possible develop a single Line Test System interface for all MPF and SMPF connections. A number of alternative schemas are being investigated but the final decision has not yet been taken. The default fall back is “No Change” and if or when that changes the details will be shared. Consult 21- Information is subject to change and is for discussion purposes only. Dates and timescales are those anticipated and maybe subject to change.

  6. Ongoing Actions LLU/11/9 - Roll Back and LLU • If Roll Back were to be required for any reason we would expect LLU to be restored to the 20CN arrangements that existed before however, as highlighted in the previous slide, the only unknown caveat at present is the access to line test equipment. LLU/11/12 - Bilaterals on Testing • Openreach do not believe the requirement from CPs/SPs/ISPs for bilaterals on CPE Testing for 21CN to be a requirement for LLU as no change to LLU service is expected. Therefore it is assumed this requested is for compatibility checks with 21CN BT Wholesale products only. Consult 21- Information is subject to change and is for discussion purposes only. Dates and timescales are those anticipated and maybe subject to change.

  7. LLU on 21CN – No change Consult 21- Information is subject to change and is for discussion purposes only. Dates and timescales are those anticipated and maybe subject to change.

  8. LLU General Update • EMP (Equivalence management Platform) phase1 has experienced some problems with Acceptance Testing which we are working hard to resolve and have therefore suspended further inputs until solutioned. • Although disappointing, but maybe not surprising with a huge system deployment of this size, this event gives justification for our decision to adopt a phased approach to this programme. • We are optimistic that the phase 1 position will be recovered by 27th February and anticipate no adverse effect on the phase 2 date of 30th June. • Be assured in the future that all tactical systems will remain in place until all migrations are complete and the new platform is stable. Consult 21- Information is subject to change and is for discussion purposes only. Dates and timescales are those anticipated and maybe subject to change.