NU-ROOF

NU-ROOF. SCHIPHOL MEETING March 1 5th 2011. D’APPOLONIA. Objectives of this meeting. Update of the test plan and responsibilities. Still on going. LAB TESTS (INCLUDING ARTIFICIAL AGEING TESTS). Results on PCM: end of march. TESTING RIG FOR ENERGY PERFORMANCE.

abra-weber
Télécharger la présentation

NU-ROOF

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NU-ROOF SCHIPHOL MEETING March 15th 2011 D’APPOLONIA

  2. Objectives of this meeting

  3. Update of the test plan and responsibilities Still on going LAB TESTS (INCLUDING ARTIFICIAL AGEING TESTS) Results on PCM: end of march TESTING RIG FOR ENERGY PERFORMANCE Start: beforenextgeneral meeting in June Start: beforenextgeneral meeting in June APPLICATION TESTS NATURAL AGEING TESTS 6 MONTHS Start: january 2012 ONE OR TWO FINAL PRODUCTS: DEMO

  4. Testing Rig PROCEDURE: 1) Start with membrane alone without back materials Assemble the 4 versionswith the polystirene Make a first runwithconstantirradiationmethod 2) Glue metal and make a secondrun 3) Glueinsulation and make a thirdrun 4) Take another set ofmembranes and gluemortar and concrete Make a fourthrunwithconstantirradiationmethod 5) Take another set ofmembranes and glueinsulation and mortar and concrete Make a fifthrunwithconstantirradiationmethod 6) Ifpcmhaseffect take the threesetsofstratigraphies and make a risingsunsimulation (wholedayuntil 18 and thenswitch off the light to simulate chargeof PCM)

  5. First general considerations on the project Testingrigis late: what are the reasonswhy the shippingfromBornerto NTUA went wrong? The associations are impatienttohearfrom some results and start collaboration on applicationprocedures, wepromised some preliminaryresultsbyApril Wp2 is due at month 16 (April): how long do wehavetopostpone wp2 delivery? When can we start sending some samplesforapplicationtests? Nextgeneral meeting = June Big disseminationevent = November

  6. Other tests: to be updated on the test plan we all have agreed