An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. S&C Electric Company U of I Power Affiliates, 2010

  2. Agenda • S&C Company Overview • Smart Grid Activity • Stored Energy • Self-Healing Systems • Communications • Real Power Engineering • ATC • Hardware • Q&A 1

  3. 100 Years of S&C Key Facts: 2

  4. 100 Years of S&C Fault Fiter® Electronic Power Fuse 1982 Liquid Power Fuse 1909 Circuit-Switcher 1959 Trans-Rupter® II 2000 Advanced Technology Center 2010 Vista® Switchgear 1996 Pad-Mounted Gear 1960 Load Interrupter Switch 1940 5

  5. S&C Organizational Structure 3

  6. Electric Delivery System The Past: Centralized, Carbon-Emitting Sources . . . The Future: Distributed, renewable electricity resources, and greater focus on reliability and efficiency 6

  7. Smart Grid

  8. The Electricity Delivery System Will be More Important Than Ever 7

  9. Definition of Smart Distribution Grids • Over used • But requires • Hardware to control the flow of current • Communications to co-ordinate activity • Storage to buffer the system and exploit renewables • S&C has all of these 8

  10. Smart Grid Initiatives 23

  11. Community Energy Storage

  12. Why CES? “Threats” of Customer-Owned-&-Operated DG Growth of Customer-Owned DG (solar) • Availability? • Reliability? • Safety? • Dispatch? “Net Zero” or “Near Zero” Customers and Areas • Own their generation (solar or wind) • Grid-Independent (with storage) • Third-party storage service could take them off the utility grid

  13. S&C’s CES ProjectHardware Overview CES is a small distributed energy storage unit connected to the secondary of transformers serving a few houses or small commercial loads 25 KVA

  14. S&C’s CES ProjectA “Virtual” Substation Battery CES is Operated as a Fleet providing Multi-MW, Multi-hour Storage • Grid Benefits: • Load Leveling at substation • Power Factor Correction • Ancillary services • Local Benefits: • Backup power • Voltage correction • Renewable Integration Utility Dispatch Center/ SCADA Integration Platform CES Control Hub Communication and Control Layout for CES Substation CES CES CES CES Power Lines Communication and Control Links

  15. Substation Storage

  16. DESS

  17. Self-Healing Systems

  18. IntelliTEAM II Case Study: Enmax • Multi-phase project • automated 66 feederswith IntelliTEAM II from 2004-2007 • Results • prevented an estimated 101,000 customer outages • saved an estimated 7,300,000 customerminutes of interruption

  19. Benefits of IntelliTEAM 11

  20. IR2 IR3 IR9 IR6 IR4 IR5 IntelliTEAM-II Self-Healing Normal circuit condition. Loss of SRC 3. 350A Max 100A Max SRC 1 SRC 2 IR1 TEAM160A TEAM2120A 0A 120A N.O. N.O. 400A Max TEAM430A TEAM370A SRC 3 SRC 4 IR7 IR8 TEAM540A 260A 0A N.O. TEAM660A

  21. IR6 IR4 IR5 IR7 IR9 IR2 IR3 IntelliTEAM-II Self-Healing IR4, IR5, IR6, IR7, and IR9 open on loss of voltage. 350A Max 100A Max SRC 1 SRC 2 IR1 TEAM160A TEAM2120A 0A 120A N.O. N.O. 400A Max TEAM430A TEAM370A SRC 3 SRC 4 IR8 TEAM540A 0A 0A N.O. TEAM660A

  22. IR4 IR2 IR5 IR7 IR9 IR1 IR8 IR3 IR7 IntelliTEAM-II Self-Healing IntelliTEAM checks loading and closes IR7 (or IR4). Restoration complete. 350A Max 100A Max SRC 1 SRC 2 TEAM160A TEAM2120A 60A 120A N.O. N.O. 400A Max TEAM430A TEAM370A SRC 3 SRC 4 IR8 TEAM540A 0A 200A N.O. TEAM660A

  23. IR2 IR4 IR5 IR6 IR9 IR3 IntelliTEAM-SG: Rapid Self-Healing Normal circuit condition. Loss of SRC 3. 350A Max 100A Max SRC 1 SRC 2 IR1 TEAM160A TEAM2120A 0A 120A N.O. N.O. 400A Max TEAM430A TEAM370A SRC 3 SRC 4 IR7 IR8 TEAM540A 260A 0A N.O. TEAM660A

  24. IR5 IR2 IR8 IR3 IR9 IR4 IR6 IR5 IntelliTEAM-SG: Rapid Self-Healing IR8 is chosen as preferred source due to higher capacity. IR5 opens and IR8 closes to restore TEAMS 1,3,4,5,6. Restoration complete! 350A Max 100A Max SRC 1 SRC 2 IR1 TEAM160A TEAM2120A 0A 120A N.O. N.O. 400A Max TEAM430A TEAM370A SRC 3 SRC 4 IR7 IR8 TEAM540A 0A 260A N.O. TEAM660A

  25. Communications – SpeedNET radio

  26. SpeedNet™ Radios: A Leading Solutionfor Self-Healing Applications 19

  27. SpeedNET Network Management Tool – Screen Shot from GUI

  28. Power Hardware

  29. Advanced Technology Centre

  30. ATC One-Line • Qty (2) 850 MVA Generators • 4.5 MVA Variable Speed Drive • 80 kA air-blast main breakers • 63 kA vacuum aux breakers • Controlled Closing Make Switch • Qty (6) 220 MVA Transformers • TRV Control • Load Simulation Components • Distribution Line Simulator

  31. Mayor Daley…Chicago Groundbreaking

  32. Starting the Generator Foundations

  33. Overhead of Generator Room

  34. Finished !

  35. IntelliRupter

  36. IntelliRupter®: A Breakthrough in Automated Switching and Protection 14

  37. Rapid Industry Acceptance R&D 100 Award Winner 17