ATCs in DB: Minnesota DOT’s Perspective

ATCs in DB: Minnesota DOT’s Perspective. Peter Davich MnDOT Design-Build Program Manager. MnDOT : ATC Statistics. DB Projects with ATCs: 22 since 2002 Total ATCs Submitted: 570 Total ATCs Approved: 352 (62%) Total ATCs Approved Without Conditions: 80 (14%)

adila
Télécharger la présentation

ATCs in DB: Minnesota DOT’s Perspective

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ATCs in DB:Minnesota DOT’s Perspective Peter Davich MnDOT Design-Build Program Manager

  2. MnDOT: ATC Statistics DB Projects with ATCs: 22 since 2002 Total ATCs Submitted: 570 Total ATCs Approved: 352 (62%) Total ATCs Approved Without Conditions: 80 (14%) ATC Utilization Rate (Incorporated into Tech Proposal): 94% ATC Categories with the Highest Success Rates: Geotechnical – 79% Grading – 74% Materials/Walls – 71% ATC Categories with the Lowest Success Rates: Paving – 46% (MnDOT now disallows some paving ATCs) Geometrics – 49% Electrical – 50%

  3. MnDOT: ATC Graphs

  4. MnDOT: ATC Graphs Continued

  5. MnDOT: ATC Cost Statistics* ATC Cost Savings over the Life of MnDOT’s DB Program: $45.0 million Cost Savings of all Approved ATCs (including unsuccessful teams): $107.4 million Individual ATCs with Largest Cost Savings: Hastings ATC#2 “Tied Arch Alternate” $4,600,000 169/494 ATC#4 “Move Ramp G” $3,000,000 TH 212 ATC#1 “TH 212 Profile Grade Change $2,300,000 Recent Project Total ATC Cost Savings: I94 Reconstruction $1,555,000 I-35E MnPASS $3,375,000 TH 169/494 Interchange $6,545,000 *Note: Cost savings are as estimated by DB Teams

  6. MnDOT: Two-Stage One-on-One Meetings • Offer meetings ~3 weeks into procurement • “Dead on Arrival” or “Entertainable” • Bring appropriate personnel • Keep meetings small, 5-on-5? • Maintain confidentiality • No: note-taking coaching (but should point out risk areas) ‘stealing’ ideas (even for some mistakes) clarifications, unless ATC-related discussion of scoring

  7. MnDOT: ATC Process Continued • # of ATCs limited (5-25) • Identify appropriate reviewers, read details carefully and write conditions carefully • Management reviews: protect DOT interests and promote innovation • Respond within 7-10 days

  8. MnDOT: Pre-Approved Elements (PAE) • Can be thought of as a required ATC • Designed to mitigate risk for both parties • “Approved” vs “Equal or Better” • Back-and-forth discussion (“coaching”) is allowed…and necessary. • MnDOT Applications • Hastings Bridge: Redundancy, Scour, Fixity, Analysis Method • TH 610: Pavement Design

  9. MnDOT Resources • Instructions to Proposers template (ATC Process): • http://www.dot.state.mn.us/designbuild/itp.html • General Design-Build Information (Laws, Project Info, Etc) • http://www.dot.state.mn.us/designbuild/ • Forms/Other: • http://www.dot.state.mn.us/designbuild/DBmanual.html • Form 2.4a for Confidentiality Template • Form 4.9a for ATC Log, 4.9b for ATC Approval Template