Project Life Cycle
30 likes | 232 Vues
Project Life Cycle. Minimum time to complete. 6 Months. Preliminary Engineering Environmental Clearance Permitting. Design Detailed Design (18 mo) Land Acquisition (3 mo) Railroad Rights of Way (1 mo) Utility Relocation (3 mo) Local Agreements with Counties
Project Life Cycle
E N D
Presentation Transcript
Project Life Cycle Minimum time to complete 6 Months • Preliminary Engineering • Environmental Clearance • Permitting • Design • Detailed Design (18 mo) • Land Acquisition (3 mo) • Railroad Rights of Way (1 mo) • Utility Relocation (3 mo) • Local Agreements with Counties • & Municipalities (1 mo) 24 Months Time 2 Months • Public Comment (15 days) • Federal Authorization (1-3 wks) • Advertise for Bid (3 wks) Shovel Ready (minimum time 32 months) 8 Months Construction • Priority to Projects expected to be completed within 3 years (2/17/12) • 50% Obligated within 120 days (8/17/09) • From H.R. 1-92 • Remaining 50% Obligated within 1 Year (2/17/10)