1 / 22

Electricity Infrastructure: Overview and Issues (2)

Electricity Infrastructure: Overview and Issues (2). H. Scott Matthews February 5, 2004. Admin Issues. HW #2 Out Today Semester Projects Groups of 1 or 2 (max) Topic on managing infrastructure Pricing can be component but should have higher-level, decision type model.

akasma
Télécharger la présentation

Electricity Infrastructure: Overview and Issues (2)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Electricity Infrastructure: Overview and Issues (2) H. Scott Matthews February 5, 2004

  2. Admin Issues • HW #2 Out Today • Semester Projects • Groups of 1 or 2 (max) • Topic on managing infrastructure • Pricing can be component but should have higher-level, decision type model

  3. Recap of Last Lecture • Source of energy changed dramatically in 100 years in US • Now mostly fuel for transport, elec all else • Electricity still mostly fossil fuel dependent • Nuclear / renewables still very limited • Electricity grid has developed as needed over time with changing requirements/demands affecting it

  4. Interstate Commerce (IC) • In early US history, states treated each other like foreign countries • Taxes, licensing, port restrictions, etc. • States had their own agreements with foreign countries (e.g. Britain) • This activity was not in ‘spirit of Union’ • Constitution gave Congress power to regulate IC (as well as foreign nations) • Note regulate was intended to mean “make uniform”

  5. Electric “Utilities” (Utils) • Electricity businesses eventually crossed jurisdictional lines and became regulated • Economies of scale - cheaper to have many users • Regulated as “natural monopoly” • Strategy was vertical integration (ownership of all local pieces - generation, trans, dist) • Started to interconnect - helps reliability, cost • Easier to regulate, but hard to control price • Recently USA decided to ‘deregulate’ and push for wholesale markets to trade power • End result: electricity sent over longer distances and through more systems than originally designed for

  6. System Statistics (End 2000) • 127 million “customers” (all sectors) • Total electric power demand = 3500 TWh/yr • Number of power plants • Non-utility: 6500 units, 208 GW (growing - dereg) • Utility: 9350, 600 GW • 154,000 miles of AC transmission lines • 3,300 miles of DC transmission lines • Next 10 yrs: 6% transmission (line-miles) growth, but 20% capacity/demand growth • Not a problem, if plants sited near demand • But, of course, its not! • http://www.eia.doe.gov/oiaf/aeo/

  7. Electric System Challenges • Unique • Instantaneous management of supply and demand • Imagine having built infrastructure that dynamically reconfigured itself to get you to your destination efficiently, without delay • Maintain 60Hz frequency • Passive Transmission • Few control valves • Just open and close switches to dispatch transmission lines

  8. Implications • Every action can affect everyone else • Need to coordinate • Cascading problems • Need to be ready for next contingency dominates design • “what if” planning • Flows near speed of light - need to act fast

  9. Diagram of U.S. Electric Power Grid Removed Due to National Security Implications (Seriously!)

  10. Blackout of November 9, 1965 • By 1965, electricity part of everyday life • Most of NE US (and Canada!) dark • Sign that we were not managing well • Six days to realize source of problem • 1 relay failed at station in Canada (Niagara Falls) • Caused transmission line to go ‘open’ • Caused series of cascading failures all the way back to New York City • Took only 15 minutes to blackout NE US • Caused people to rethink dependence • Until then, power systems design geared around ‘isolation’ to prevent damage

  11. As a Result of 1965 Blackout.. • Consumers made contingency plans • As did firms and large industrial users • At high/policy levels, coordinating entities were formed to manage • North American Elec. Reliability Council (NERC) • New York Power Pool (NYPP) • Developed industry equipment standards • Developed reserve gen. capacity • Interconnection and reliability methods • Isolation had led to islands/points of failure • Now we more heavily ‘network’ the system so there are multiple paths for power to flow

  12. NERC • Voluntary organization to promote reliability • Alternative to being regulated • Sets standards, collects data, etc. • No longer sufficient after dereg. Three major interconnected power systems in US that coordinate actions to keep reliability

  13. Reliability Components • Adequacy • Does (projected) Supply = Demand? • A long-term planning process • Security • Robust system against failures (short-term) • NERC transitioning to have enforcement power to meet reliability

  14. Electric Power ‘Jurisdiction’ • FERC - Fed Energy Regulatory Comm. • Regulates trans/sale of energy and fuels • Electricity : regulate bulk power • Oversees environmental issues • Budget from fees to regulated firms • NERC (already done) • Control Areas - fundamental entity (150) • Vary: PJM (50,000 MW) others 100 MW • Regional Reliability Councils (10) • Interconnects (3) • Note State PUCs not mentioned

  15. Deregulation Effects • Transmission built primarily over 100 years by vertically integrated utilities • Originally built close to fuel supply • Recap: at first only local transmission built • Some interconnections built for reliability, relief • Utils cooperated - in mutual best interest • Dereg. sought to lower elec prices by: • Making capital available for new capacity • Increasing efficiency of operations • Trans. grid ‘interstate’ for wholesale electricity • But highway congestion just means delay • Electric transmission congestion = lost energy!

  16. Deregulation (cont.) • Now > 50% of power sold wholesale first • Congestion - demand & construction of new generation not matched with new trans. • Incentives to cooperated reduced • What happened in California? Depends! • Imbalance in supply/demand - not much new supply approved for construction, demand higher • Big part of problem was faulty market design • Lack of adequate transmission for competitive power to come into market to ease prices • 1996: FERC opened ‘wires’ to non-utilities • Basically opened market to competition

  17. Energy Policy Act - 1992 • 1980s: electricity trading had taken off • Act pushed trading: Gen & Trans competition • Non-utils to have power plants • By 1998: nonutils 13% market share • Called Independent Power Producers (IPP) • Don’t forget regulatory process! • Congress : laws + authority, implementation : agencies • FERC Order 888: encouraged ISOs • Independent System Operators • Independent of commercial interests • Could own no generation

  18. Recent changes • ISOs - Independent System Operators • Open and fair access to regional grid; non-discriminatory governance structure; facilitating wholesale electric rates; independent - don’t own gen/trans • 1999: FERC Order - RTOs • Regional transmission organizations

  19. Factors for Transmission and Distribution Losses • Location of generating plant and load connection points (how close to demand) • Types of connected loads • Network configuration • Voltage levels and voltage unbalance • Dynamic factors (e.g. power factor, harmonics, control of active and reactive power) • Length of the lines - almost linear relationship • Current in line - a square law relationship • Design of lines, particularly the size, material and type of cables • California / US about 10%

  20. Cost Issues • Average electricity price 7 cents/kWh • Decreasing by new const and coal prices • Expected demand growth 2%/yr til 2020 • Transmission costs ~10% of total cost • Resulting bottlenecks cause short-term price increases and thus higher costs! • Problem areas California, PJM, NY, New England • $500M / yr in these areas alone

  21. Management Metrics • Capacity Margin = Generation/Demand • Base load - min. amount electricity required over a given time interval, at steady rate • Peak load - max load requirement during a given time interval • Intermediate load - between base & peak

  22. Energy Balance for Typical Coal Plant http://www.energy.qld.gov.au/electricity/infosite/elec&env7/roleofenergy7_3/efficiencyinpowerstat/energylosses/energylosses.htm Energy Balance for Typical Coal Plant

More Related