An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RE1/2 and RE1/3 Gap Status & QC - 2005 CMS week March 2005 Piritta Kaarlola

  2. Gap QC • Gap QC consists of HV, Spacer and Gas Leakage test • HV test • Applied HV values: 2000, 4000, 6000, 8000, 8500, 9000 & 9100 • Resulted currents must stay within the range from 0.50 µA to 3.00 µA • Spacer test • Gas input and output are connected with 20 mbar overpressure • Allowed change: ± 0.5 mbar • Gas Leakage test • Gas input and output are connected with 20 mbar overpressure • Allowed gas leakage: max. -0.5 mbar • Another QC issue: bent gaps • Allowed bending <10mm For the moment used for spares

  3. RE1/2 Gap status • Chambers • None ready – Production not yet started • 60 needed (180 gaps) • Gaps • Current holdings • Small: 18 • Medium: 13 • Big: - • Still needed • Small: 42 • Medium: 47 • Big: 60

  4. RE1/3 Gap status • Chambers • 13 ready chambers (39 gaps) • 47 needed chambers (141 gaps) • Gaps • Current holdings • Small: 9 • Medium: 7 • Big: 2 • Still needed • Small: 38 • Medium: 40 • Big: 45

  5. RE1/3 QC – HV Test Average currents of HV tested gaps

  6. RE1/3 QC - Spacer and Gas Leak Test • Spacer Test: • 1 small gap rejected • Gas Leak Test • Very little or no leak – no rejected gaps • Bent gaps • 5 big gaps