The Impact of Uncertain Future RES-E Deployment on the Electricity System - An Evaluation for Germany. Michaela Fürsch , Stephan Nagl. IAEE Conference Stockholm, 22/6/2011. Content. Motivation 2. Methodology Multistage- Stochastic Investment and Dispatch Model Scenario tree

alessa
Télécharger la présentation

Michaela Fürsch , Stephan Nagl

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Impact of Uncertain Future RES-E Deployment on the Electricity System -An Evaluation for Germany Michaela Fürsch, Stephan Nagl • IAEE Conference Stockholm, 22/6/2011

  2. Content • Motivation 2. Methodology • Multistage-Stochastic Investment andDispatch Model • Scenario tree 3. Results • Optimal electricity mix underuncertainty • Costsofuncertainty 4. Conclusions

  3. Motivation – RES-E deployment in Germany since 1990

  4. Motivation – Underestimationofcurrent RES-E deployment

  5. Motivation – Future RES-E deploymentisuncertain

  6. Research question: Consequencesofuncertainty Uncertaindeploymentof RES-E (policy-drivenpartofelectricitysystem) Uncertaintyaboutlevelandstructureof residual load Competitivepartofelectricitysystem: longplanning, construction, amortizationtimes Consequencesofuncertainty Multistage stochastic model: Optimal electricity mix underuncertainty Deterministicsolutionsofbranches: Optimal electricity mix undercertainty

  7. Multistage stochastic Investment andDispatch Model • linear dynamicinvestmentanddispatch model • minimizes total (discounted) systemcosts • neededtofulfill residual demand in eachscenarionode • consideringoccurenceprobabilityofeachnode • Optimal electricity mix underuncertainty

  8. Multistage stochastic Investment andDispatch Model Determination ofInstalledCapacity in node n iftechnicallifetime exceeded n2, n1 n1 n (…) n1 n: „current“ node n2: directancestorof n n1: all directandindirectancestorsof n (…) (…)

  9. Scenario treebased on RES-E scenariosandforecastsfor Germany high high Adjustedinvestments high high low low > NREAP 2020 high high high high low low low low NREAP2015 NREAP 2020 (…) high high < NREAP 2020 (…) low low Optimal investmentunderuncertainty 2010 high high high high low low high high NREAP 2020 high high low low low low < NREAP 2015 < NREAP 2020 (…) low low

  10. Scenario tree – resulting residual loadcurve (2050)(Scenario 1 (max. RES-E) vs. Scenario 20 (min RES-E)) Res. Load = load – fluctuating RES-E

  11. Deterministic vsstochastic: - 5 GW Coal - 2 GW CCGT Results Stochastic Solution InstalledCapacity > NREAP 2020 ++ NREAP2015 NREAP 2020 ++ CAP_ADD 6.9 lignite 5,1 coal 3.4 CCGT 0.5 OCGT < NREAP 2020 + Fullloadhours 2010 • Deterministic • vsstochastic: • + 10 GW Coal • - 4 GW CCGT < NREAP 2015

  12. Results - Costs Extra costsofstoch. solution SevereConsequencesofuncertainty? • Extra costsseem not verysignificant, • compared e.g. to RES-E promotioncosts in 2010 • BUT: • Extra costsdepend e.g. on gas-coalspread, discount rate etc. • onlycostsif form ofuncertaintyisknown

  13. Conclusions 1 Uncertain RES-E deploymentpaths => Uncertaintyaboutlevel + structureof residual load 2 Uncertaintyleadsto suboptimal electricity mix 3 Uncertaintyinduces extra costs (depending e.g. on gas-coalspread) Benefitofflexibility in RES-E policyhastobeweightedagainstcostsofuncertainty

  14. Thank you for your audience. Questions, comments? Contact: Michaela Fürsch Michaela.Fuersch@uni-koeln.de