PERT / CPM

PERT / CPM. PERT Program Evaluation & Review Technique CPM Critical Path Method. A Simple Project. Project Network. ES Earliest Starting (time) EF Earliest Finishing LS Latest Starting LF Latest Finishing Slack Extra Time. Earliest Starting/Finishing Times. EF = ES + t.

Télécharger la présentation

PERT / CPM

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PERT / CPM PERT Program Evaluation & Review Technique CPM Critical Path Method

  2. A Simple Project

  3. Project Network

  4. ES Earliest Starting (time) EF Earliest Finishing LS Latest Starting LF Latest Finishing Slack Extra Time

  5. Earliest Starting/Finishing Times EF = ES + t

  6. LS = LF - t

  7. What if activity times are variable? a optimistic time m most likely time b pessimistic time t = E(T) expected time = (a + 4m + b)/6 V(T) variance = (b - a)2/36

  8. Activity TimeExpected Value and Variance

  9. Possible Paths and Statistics

  10. What is the probability that the project takes at least 10 days? • What is the probability that the project takes less than 7 days?