An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Fort Detrick Installation Restoration Program IRP Manager US Army Garrison

  2. Fort Detrick Area B-11 Pit 1 Removal Project Status View of Completed Backfill • No lost time accidents (765 days) • SITUATION AS OF 28 APRIL: • Pit #1 removal action is complete (ended 21 March 2003). • Removed 2005 tons of waste and contaminated soil from the pit (112 rolloffs). 175 tons non-hazardous overburden to Fort Detrick's landfill. Recovered over 40 drums, 113 vials, 50 cylinders • Equipment inside structure has been decontaminated and removed. • Confirmatory wipe biological samples were collected and indicated no pathogenic bacteria remain. • Backfill completed. Hydroseeding to occur after Pits #2, 3, and 4 excavation complete. • Pits #2, 3, 4 mobilization began 21 March 2003 Backfill of Pit #1 Cleaning/Disinfecting Equipment Environmental Quality Control Committee

  3. Fort Detrick Area B-11 Pits 2, 3, 4 Removal Project Status Containment Structure Moved Over Pits #2, 3, and 4 Structure Moved 23-24 March 2003 Environmental Quality Control Committee

  4. Fort DetrickArea B-11 Pits 2, 3, 4 Removal Project Status (cont.) • Pits 2, 3, and 4 Schedule • Startup activities: 21 March 2003 – 02 May 2003 • Excavation: 08 May 2003 – 28 Nov 2003 • Demob/Decon: 01 Dec 2003 – 23 Jan 2004 • Site Restoration: 26 Jan 2004 – 05 Feb 2004 • Funding • FY02 and FY03 Funds programmed for Pits 2, 3, and 4 were awarded week of 31 March 2003. Environmental Quality Control Committee

  5. Fort Detrick Installation Restoration Program Contact Information: IRP Manager USAG Environmental Management Phone 301-619-3196