Sample Questions for Microsoft Certification Exam 70-632

Sample Questions for Microsoft Certification Exam 70-632. Microsoft Office Project 2007: Managing Projects. What tool do you use to identify tasks whose Finish date cannot slip without impacting the Finish date of the project?. Gantt Chart Wizard Task Drivers pane Change Highlighting

anais
Télécharger la présentation

Sample Questions for Microsoft Certification Exam 70-632

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Sample Questions for Microsoft CertificationExam 70-632 Microsoft Office Project 2007: Managing Projects

  2. What tool do you use to identify tasks whose Finish date cannot slip without impacting the Finish date of the project? • Gantt Chart Wizard • Task Drivers pane • Change Highlighting • Resource Usage view NOTE: Use the Gantt Chart Wizard to format the Critical Path using red Gantt bars.

  3. What feature do you use to display summary information for the entire project, such as total Work and Cost? • A Milestone task at the end of the project • Project Summary Task • Task Drivers pane • A series of tasks linked with a Finish To Start dependency

  4. What feature should you use to specify an overall monetary budget for your entire project? • Budget Cost resource • Budget Work resource • Expense Cost resource • Expense Work resource

  5. Which default View should you use to compare the current project schedule against the original Baseline schedule? • Gantt Chart view • Resource Usage view • Leveling Gantt view • Tracking Gantt view

  6. Which Leveling option must you select to guarantee that Leveling does not change the Finish date of your project? • Set the Leveling Order to Priority, Standard • Leveling Can Adjust Individual Assignments on a Task • Level Only Within Available Slack • Leveling Can Create Splits in Remaining Work

  7. What feature do you use to determine the reason for the scheduled Start date of any task in your project? • Change Highlighting • Gantt Chart Wizard • Project Summary Task • Task Drivers pane

  8. How do you enter company holidays as nonworking time in your Microsoft Project 2007 plan? • Use task splits to split work around a holiday • Enter nonworking time on the Standard calendar • Manually increase the Duration of tasks that occur during the company holiday • Add “dummy tasks” to represent the holidays

  9. Which default Table do you use to compare the current Start/Finish dates with the Baseline Start/Finish dates? • Baseline table • Schedule table • Variance table • Tracking table

  10. Which feature do you use to display project data graphically in Microsoft Office Excel or Microsoft Office Visio? • Change Highlighting • Gantt Chart Wizard • Save the project as an Adobe PDF document • Visual Reports

  11. Which feature can you use to emphasize particular tasks, such as new tasks added through Change Control? • Change Highlighting • Cell Background Formatting • Task Drivers • Visual Reports