This document outlines the anticipated milestone schedule for the Acquisition Strategy Industry. Key events include the issuance of draft sections L and M of the DRFP on February 28, 2011, followed by the Industry Day on March 24, 2011. The final RFP will be issued on May 15, 2011, with proposals due by July 6, 2011. The SSA decision is set for November 21, 2011, followed by draft contract documents on December 4, 2011, culminating in the award on December 30, 2011. Approved for public release with unlimited distribution.
E N D
D3I TENATIVE MILESTONE SCHEDULE Anticipated EventCompletion Date Acquisition Strategy Industry Day Late Jan 2011 Issue Draft Sections L and M of DRFP 28 Feb 2011 DRFP Industry Day 24 Mar 2011 Issue Final RFP 15 May 2011 Proposals Due 06 Jul 2011 SSA Decision 21 Nov 2011 Draft Contract Documents 04 Dec 2011 Award 30 Dec 2011 DISTRIBUTION A. Approved for public release; distribution unlimited.