An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. INSTALLATION OF LSS (Experimental insertions) S.Bartolomé - EDMS:547511

  2. OUTLINE • Critical case: sector 7-8 • LSS before installation of the beam line components • Provisional installation sequence of LSS8R (8-1) • Experimental insertions specificities • Summary S.Bartolomé - EDMS:547511

  3. LSS8L CRITICAL CASE: SECTOR 7-8 • Installation by CERN of the QRL in sector 7-8 gives the opportunity to: • Start with QRL sub-sector A and B (~600m left of point 8 (LSS8L)) in March 2005 and then, install magnets in parallel with the remaining of the QRL • Start QRL cold testing in June 2005 • Start installing magnets (LSS8L) in parallel with the remaining of the QRL in August 2005 • LSS8L cool down & power tests from October 2005 to March 2006 • Gather maximum experience on the field in 2005 with a view to propose an optimized and reliable scenario for the other sectors S.Bartolomé - EDMS:547511

  4. CRITICAL CASE: SECTOR 7-8 (cont.) • The following main diverse material have to be available for installation in Summer 2005: • Components: • Support jacks (supplied by CAT-India) • Motorised jacks for Inner Triplets: CAT-India jacks modified • Resistive magnets: MBXW and MBXWS • Inner Triplet (Q1-Q2-Q3) • DFBXG • D1-D2 • Collimator, TCL • Q4, Q5 • DFBMA/C S.Bartolomé - EDMS:547511

  5. CRITICAL CASE: SECTOR 7-8 (cont.) • Installation tooling such as: • Spreader beams for all magnets • Transportation system for DFBX • Vacuum equipment: • Cold-warm transitions (VAX, VAB,…) • Vacuum chambers • Supports • Beam position monitors (BPTX, BPMWB, BPMSW, BPMSX…) • Instrumentation • Others S.Bartolomé - EDMS:547511

  6. No-coactivity during power converters short circuit tests! No-coactivity during cool-down! Powering test possible co-activity with vacuum (bake-out and NEG activation) S.Bartolomé - EDMS:547511

  7. LSS BEFORE INSTALLATION OF THE BEAM LINE COMPONENTS • General requirements: • General services installed • Tunnel floor prepared for support jacks installation • QRL installed • DC cabling installed • Control and signal cabling installed • HLS (Hydrostatic Level System) and WPS (Wire Positioning System) preinstalled (where applicable) • And…where required: • Installation of transfer rails for Q1-Q2 installation (RB14, RB16, RB26, R542, R561, RB86) • Installation of shielding plugs (RPX24, RB26, RB84, RB86) S.Bartolomé - EDMS:547511

  8. LSS8R PROVISIONAL INSTALLATION SEQUENCE OF LSS8R (8-1) • Starting point: • QRL installation finished by June 2005 • QRL commissioning in August and September 2005 • Installation sequence of LSS8R: • Shielding in RB86 • Support jacks • Beam line elements installation: • Resistive magnet (MBXWS) • Inner Triplet and D1 • DFBXH • D2, Q4, Q5 • TCDD, TDI, MKI, MSI S.Bartolomé - EDMS:547511

  9. Oct-Dec 2005 S.Bartolomé - EDMS:547511

  10. PROVISIONAL INSTALLATION SEQUENCE OF LSS8R(8-1) (cont.) • Alignment (Q1  Q5) • Magnets interconnection and closure (DFBX included) • DFBMA/C: transport and installation • Vacuum: • Install and connect components (Q1  Q5) • Install and connect standalone sectors (D2/Q4, Q5) • Install and connect components (warm sectors) • Reception, bake-out and NEG activation (warm sectors) • Power cables connections, signal cables, cooling and control components • Installation of survey equipment: HLS and WPS S.Bartolomé - EDMS:547511

  11. Nov 2005-Nov 2006 S.Bartolomé - EDMS:547511

  12. F. DELSAUX 27/04/2004 RB 84 Shielding F. DELSAUX 27/04/2004 QRL RB86 Shielding MBXWS RB 86 (28 April 2004) EXPERIMENTAL INSERTIONS SPECIFICITIES: IR8 • RB84: • Starting point: steel shielding installed • Standard installation of Inner Triplet  LSS transport vehicle and transfer tables • RB86: • Starting point: main part of shielding installed • Q1 installation: transfer with rails and motorised bogies S.Bartolomé - EDMS:547511

  13. RB14 Shielding UX 15 Holesfor Q1 motorised Jacks EXPERIMENTAL INSERTIONS SPECIFICITIES: IR1 • HLS and WPS preinstalled • Installation of steel-welded structure for continuing the rails and personnel access inside the ATLAS forward shielding tube TX1ST. • Installation of 2xQ1: transfer with rails and motorised bogies S.Bartolomé - EDMS:547511

  14. RPX24 EXPERIMENTAL INSERTIONS SPECIFICITIES: IR2 • RB24: • Starting point: RPX24 supporting structure and shielding installed PX24: used to lower down special magnets! S.Bartolomé - EDMS:547511

  15. EXPERIMENTAL INSERTIONS SPECIFICITIES: IR2 • RB26: • Starting point: main part of shielding installed • Installation of Q1 and Q2: transfer with rails and motorised bogies S.Bartolomé - EDMS:547511

  16. Point 5: Q1 located in UXC55 and R542/R561 CMS Shielding opening approx. 4x2x2(m) UPS galleries for alignment purposes EXPERIMENTAL INSERTIONS SPECIFICITIES: IR5 • HLS and WPS preinstalled • Installation of 2xQ1 and 2xQ2: transfer with rails and motorised bogies S.Bartolomé - EDMS:547511

  17. SUMMARY • Installation dates: • LSS8L  August 2005 • LSS8R  October 2005 • LSS1L  October 2005 • LSS5L  December 2005 • LSS5R  April 2006 • LSS2L  July 2006 • LSS1R  August 2006 • LSS2R  September 2006 • Each LSS is a particular case due to the specific configuration of the area and safety constraints such as: restriction on co-activities, on transports, on access during pressure tests, cold down and electrical tests. • A Schedule Change Request (SCR) will be required for each LSS. S.Bartolomé - EDMS:547511