An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Water Plant #3Concentrate Pre-treatmentProject

  2. Water Plant #3 Concentrate Pre-treatment Project Project Goals • Meet Strategic Action Plan Performance Measure Strategy 4.1.1: Utilize nature’s water supply resources effectively for water supply • Meet the Conservation Policy Principles of The City • Meet the Best Management Practices of the St. Johns River Water Management District • Meet the Department of Environmental Protection regulatory requirements

  3. Regulatory Requirements: • WTP#3 has a discharge permit limit for iron of 0.3 mg/L • WTP#3 Concentrate is greater than 0.3 mg/L • Florida Department of Environmental Protection Administrative Order 154NE provides a schedule to meet the iron discharge limitation • Concentrate is permitted as a source water at WTP#1 • Color Compliance at WTP #1 is dependent on color reduction treatment by ozone treatment at WTP#3 Water Plant #3 Concentrate Pre-treatment Project

  4. Water Plant #3 Concentrate Pre-treatment Project Contractor Selection • Sawcross Inc. was determined to be the low bidder at the Bid opening on May 1, 2014 to complete the Concentrate Pre-treatment Project at Water Plant #3 • At the May 13, 2014 workshop, staff presented the SawcrossInc. contract for Council consideration • Signing of the construction contract was held in abeyance until the State appropriated the $375,000.00 grant funding for the project

  5. Process Components: Primary System • Ozone system for color reduction • Recovers up to 750,ooo gallons per day Secondary System • Cartridge filtration system for iron reduction Water Plant #3 Concentrate Pre-treatment Project

  6. Water Plant #3 Concentrate Pre-treatment Project Funding: • Total Project Budget - $1,580,000 • Design & Permitting - $162,345 • Construction Cost including contingency - $1,407,680 • Source of Funds: 5 Year CIP bond funds • St. Johns River Water Management District (SJRWMD) Cooperative Cost Share Grant - $494,800 • Florida Legislative Funding Grant - $375,000

  7. Water Plant #3 Concentrate Pre-treatment Project July 15, 2014 Council Actions: • Resolution to initiate a Construction Contract with Sawcross Inc. for improvements at Water Plant#3 • Resolution to authorize the City Manager to finalize a Department of Environmental Protection Grant Funding agreement

  8. Water Plant #3 Concentrate Pre-treatment Project Questions?