1 / 13

Bulk Electric System Definition Task Force Update

Bulk Electric System Definition Task Force Update. Reliability Policy Issues Committee March 4, 2010 Brian Theaker BESDTF Chair. Today’s Update. BES definition proposal Material Impact Assessment Schedule Questions. December 2009 RPIC Guidance .

asasia
Télécharger la présentation

Bulk Electric System Definition Task Force Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Bulk Electric System Definition Task Force Update Reliability Policy Issues Committee March 4, 2010 Brian Theaker BESDTF Chair

  2. Today’s Update • BES definition proposal • Material Impact Assessment • Schedule • Questions

  3. December 2009 RPIC Guidance • Phase 1 – focus on what Elements are part of the BES • Transmission voltage performance • Targeting OC approval in June • Phase 2 – evaluate how entities may impact BES reliability • Generators • Loads • Scope and timing undefined

  4. Recent Events • Posted on February 12: • Proposal 4 • MIA status (Appendix A) • BES white paper (Appendix B) • Response to comments on P3 • Comments on P4 due 3/17

  5. Proposal 4 • Reformatted for clarity, eliminate conflict • Tightened up “radial exemption” • < 200 kV, serving only load, not hard-tapped • Distribution Networks • Networks > 100 kV that serve load and do not provide “meaningful flow-through” • Seeking to define in a way that would allow exclusion from BES without an MIA • Struggling and seeking comment

  6. Proposal 4 – (2) • Points of demarcation • Automatic fault interrupting device • Is AFID part of BES? • Complex connections (ring bus, breaker-and-a-half) • Protection systems and PRC-004/005

  7. Proposal 4 – (3) • Exclude Elements not represented in WECC-SRWG Annual Study Plan Basecases • Will be controversial - expect comments

  8. Material Impact Assessment • Process must be: • Clear and objective • Technically defensible • Accessible • Repeatable • Concerns: • Regulatory approval (NPCC experience) • Burden on smaller entities without study capabilities • Burden on WECC staff to review • Administrative process – logging, renewal, etc.

  9. Material Impact Assessment • Phase 1 – focused on: • Transmission voltage performance • Classifying BES Elements • Two approaches: • Three-phase fault with delayed clearing • Scan for significant and widespread impacts • Short-circuit MVA

  10. Material Impact Assessment (2) • TSS review • Discussed with TSS on 1/20 • TSS has formed task force to consider • Use of three-phase fault with delayed clearing • Generator and load tripping inevitable • How much / what kind of tripping is allowed? • Can alternate approaches be combined? • Use SCMVA approach as a “screen” to reduce number of simulation studies?

  11. Schedule • Fourth Proposal posted on 2/12 • Presenting to joint MIC/OC/PCC meeting on March 11 • Seeking OC feedback

  12. Schedule (2) • Continue to develop MIA • TSS and BESDTF MIA small group • Post MIA for 45-day comment period • Seek OC approval of BES definition and MIA in June (?) • Waiting for TSS input makes June impossible • Six-month gap between October and March • Phase 2 - TBD

  13. Questions? For every complex problem there is an answer that is clear, simple, and wrong. H.L. Mencken Things should be made as simple as possible, but not any simpler. Albert Einstein Brian Theaker Chair, BESDTF brian.theaker@dynegy.com

More Related