OPSM 50 1 : Operations Management

Ko ç Un iversity Graduate School of Business MBA Program. OPSM 50 1 : Operations Management. Week 5: Batching EOQ. Zeynep Aksin zaksin @ku.edu.tr. High-Inventory Manufacturing. Order : 1000 units. 4 months (24 hrs a day, 7 days a week). A : 1/2 hr/unit. inventory. B : 1/10 hr/unit.

azia
Télécharger la présentation

OPSM 50 1 : Operations Management

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Koç University Graduate School of Business MBA Program OPSM 501: Operations Management Week 5: Batching EOQ Zeynep Aksin zaksin@ku.edu.tr

  2. High-Inventory Manufacturing Order : 1000 units 4 months (24 hrs a day, 7 days a week) A : 1/2 hr/unit inventory B : 1/10 hr/unit avg. inventory C : 1 hr/unit B : 1/10 hr/unit D : 3/4 hr/unit 1000 2000 Time (hours)

  3. Low-Inventory Manufacturing Order : 1000 units 2 months Move batches of 200 Release materials according to the bottleneck A : 1/2 hr/unit B : 1/10 hr/unit C : 1 hr/unit inventory B : 1/10 hr/unit avg. inventory D : 3/4 hr/unit 1000 2000 Time (hours)

  4. When do you detect quality problems? Quality control A B C B D Damage done

  5. How do you incorporate engineering changes? A B C B D Engineering change one month after start of order

  6. Shorter Lead time - High margins Quoted lead time of the order is 3 months A B C B D overtime No overtime

  7. Due-date performance A B C B D Forecast validity

  8. Batch Flow Operations Carry a Lot of Inventory • SMED (Single minute exchange of die): reduce set-up times

  9. Things that influence flow time • Process control • Lotsize • Before I move from one product run to another, how much will I produce • Physical constraints • Customer order size • Managerial decisions • Set-up time/production time

  10. Batching in practice • Common in low volume manufacturing (including a lot of high-tech) • Also: transportation, education / training • Example: mailing list development • Creates an inherent mismatch between demand and supply

  11. Lotsize decision • Three products: P1, P2, P3 • Produce 100 units of each • Alternatives • 100 P1 100 P2 100P3 • 1P1 1P2 1P3 1P1 1P2 1P3 • 100 times • Set-up time • Cutting tools, cleaning, calibration, loading programs, etc.

  12. Set-up times • Set-up time does not depend on lotsize and is the same for all lotsizes. • Production time depends on lotsize • Not always (baking, heat treat) • Long set-up timeslarge lotsizes

  13. Example • P1,P2,P3 example • Set-up time 60 min. • Production time 10 min/unit • Need 3 of each type • Try the alternatives • 1P1, 1P2, 1P3, 1P1, 1P2, 1P3, 1P1, 1P2, 1P3 • 3P1, 3P2, 3P3

  14. Product Space, Efficient frontier Responsiveness High Reduce set-up times Smaller batches Now Larger batches Higher frontier Low High perunit costs Low perunit costs Costs

  15. Process Analysis with Batching 0.5 1/p Capacity 0.45 0.4 0.35 0.3 0.25 0.2 0.15 Capacity given Batch Size= 0.1 0.05 0 Batch Size Batch Size 10 50 90 130 170 210 250 290 330 370 410 450 490 530 570 610 650 Set-up time + Batch-size*Time per unit • Capacity calculation changes: • Note: Capacity increases with batch size: • Note further: … and so does inventory (and thus flow time) See chapter 5

  16. Example Milling S=120 min p= 2 min/unit Assembly S=0 p=3 min/unit B=12? B=300? Recommended B=?

  17. warehouse retailer Economies of Scale:Inventory Management for a Retailer The South Face retail shop in the SapphireTower has observed a stable monthly demand for its line of Gore-Tex jackets on the order of 100 jackets per month. The retail shop incurs a fixed cost of $2,000 every time it places an order to the Adana warehouse for stock replenishment. The marginal cost of a jacket is $200, and South Face’s cost of capital is approximately 25%. What order size would you recommend for The South Face?

  18. Inventory Profile: # of jackets in inventory over time. Inventory Q R = Demand rate Time t Economies of Scale: Inventory Build-Up Diagram R: Annual demand rate, Q: Number of jackets per replenishment order • Number of orders per year = R/Q. • Average number of jackets in inventory = Q/2 .

  19. Find most economical order quantity: Spreadsheet for The South Face

  20. Annual Purchasing Cost Annual Ordering Cost Annual Holding Cost Total Annual Cost = + + Total Annual Cost • Using calculus, we can take the derivative of the total cost function and set the derivative (slope) equal to zero • We can also use economic intuition

  21. Total annual costs H Q/2: Annual holding cost S R /Q:Annual setup cost EOQ Batch Size Q Economies of Scale: Economic Order Quantity EOQ R : Demand per year, S : Setup or Order Cost ($/setup; $/order), H : Marginal annual holding cost ($/per unit per year), Q : Order quantity. C : Cost per unit ($/unit), r : Cost of capital (%/yr), h:Physical unit holding cost ($/unit,yr), H = (h + r) C.

  22. EOQ Model: if there is a lead time L QEOQ # Units on hand ROP Time L L ROP = Reorder point L = Lead time (constant) Q = Economic order quantity

  23. Economic Order Quantity (EOQ) Model • Economic Order Quantity (EOQ) Model • Robust, widely used • Insensitive to errors in estimating parameters (40-20-2 Rule): • 40% error in one of the parameters • 20% error in Q • < 2% of total cost penalty

  24. Learning Objectives: Batching & Economies of Scale • Increasing batch size of production (or purchase) increases average inventories (and thus cycle times). • Average inventory for a batch size of Q is Q/2. • The optimal batch size trades off setup cost and holding cost. • To reduce batch size, one has to reduce setup cost (time). • Square-root relationship between Q and (R, S): • If demand increases by a factor of 4, it is optimal to increase batch size by a factor of 2 and produce (order) twice as often. • To reduce batch size by a factor of 2, setup cost has to be reduced by a factor of 4.

  25. Announcements • HW 2 is due next time • The Goal is due next time • Have a nice break!