An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Management PERT ___________________________________________________________________________ Operations Research  Jan Fábry

  2. Expected completion time Project Management PERT • Probabilistic time – 3 estimates Optimistic Pessimistic Most likely ___________________________________________________________________________ Operations Research  Jan Fábry

  3. Most Likely Expected Optimistic Pessimistic Time 0 aij mij μij bij Project Management PERT • Activity time β-distribution ___________________________________________________________________________ Operations Research  Jan Fábry

  4. Project Management PERT • Expected completion time • Standard deviation ___________________________________________________________________________ Operations Research  Jan Fábry

  5. Critical path Project Management PERT 1) Using CPM ( tij= μij) 2) Expected duration of the project Variance of the project duration ___________________________________________________________________________ Operations Research  Jan Fábry

  6. T M -σ M M + σ Project Management PERT Duration of the project - normal distribution M – expectedduration T – realduration σ– standarddeviation ___________________________________________________________________________ Operations Research  Jan Fábry

  7. probabilty of completion time within TD p Project Management PERT 3) Probability analysis desired time TD desired time TD ___________________________________________________________________________ Operations Research  Jan Fábry

  8. completiontime zp Project Management PERT 3) Probability analysis desired probability p desired probability p ___________________________________________________________________________ Operations Research  Jan Fábry

  9. Project Management PERT Example - Music DM, Inc. ___________________________________________________________________________ Operations Research  Jan Fábry

  10. Project Management PERT Example - Music DM, Inc. ___________________________________________________________________________ Operations Research  Jan Fábry

  11. H K B D2 J A D G I D1 C F E 8 5 6 4 7 3 9 10 2 1 Project Management PERT Example - Music DM, Inc. Critical path: ___________________________________________________________________________ Operations Research  Jan Fábry

  12. Project Management PERT Example - Music DM, Inc. Critical activities ___________________________________________________________________________ Operations Research  Jan Fábry

  13. Expected duration of the project M = 48 Variance of the project duration  2 = 9 Std. deviation of the project duration  = 3 Project Management PERT Example - Music DM, Inc. ___________________________________________________________________________ Operations Research  Jan Fábry

  14. Time (days) 45 48 51 Project Management PERT Example - Music DM, Inc. Duration of the project ___________________________________________________________________________ Operations Research  Jan Fábry

  15. Project Management PERT Example - Music DM, Inc. Probability analysis Desired time TD = 45 ___________________________________________________________________________ Operations Research  Jan Fábry

  16. zp = 1.645 Project Management PERT Example - Music DM, Inc. Probability analysis Desired probability = 0.95 ___________________________________________________________________________ Operations Research  Jan Fábry

  17. Inventory Models ___________________________________________________________________________ Operations Research  Jan Fábry

  18. Inventory Models Inventory • Stored for use in future • Examples of inventories - raw material - finished goods - semi-finished products - spare parts ___________________________________________________________________________ Operations Research  Jan Fábry

  19. Inventory Models Reasons for Maintaining Inventories • Fluctuating demand • Delayed supply • Savings on ordering cost • Benefits on large quantities • Inflation ___________________________________________________________________________ Operations Research  Jan Fábry

  20. Inventory Models Management • How much to order? • When to order? • Objective – minimize total cost ___________________________________________________________________________ Operations Research  Jan Fábry

  21. frequency of ordering cost Inventory Models Partial Inventory Cost • Ordering & setup cost – fixed charge • Unit purchasing cost – variable cost quantity discounts ___________________________________________________________________________ Operations Research  Jan Fábry

  22. Inventory Models Partial Inventory Cost • Holding & carrying cost – variable cost - storage cost (space) - store keeping operations (movement) - insurance & taxes - interest (invested capital ) - oportunity cost - spoilage or obscolescence ___________________________________________________________________________ Operations Research  Jan Fábry

  23. Inventory Models Partial Inventory Cost • Shortage (stockout) cost – variable cost - idled production (idled machine) - placing special expensive expediting order - loss of customers due to late deliveries ___________________________________________________________________________ Operations Research  Jan Fábry

  24. Inventory Models Inventory Terminology • Inventory level Available size of the inventory • Demand & depletion Rate of demand  Depletion rate ___________________________________________________________________________ Operations Research  Jan Fábry

  25. Lead time Time Placing order Receiving shipment&Replenishment Inventory Models Inventory Terminology • Reordering Reorder point = signal inventory level ___________________________________________________________________________ Operations Research  Jan Fábry

  26. Receiving shipment Shortage !! Lead time Time Optimal reorder date Inventory level = 0 Placing order Inventory Models Inventory Terminology • Shortage ___________________________________________________________________________ Operations Research  Jan Fábry

  27. Inventory Models Inventory Terminology • Safety stock Buffer being built to prevent shortage In case of probabilistic demand ___________________________________________________________________________ Operations Research  Jan Fábry

  28. Inventory Models Inventory Models • Deterministic models Rate of demand is known with certainty • Probabilistic models Probabilistic demand (random variable) ___________________________________________________________________________ Operations Research  Jan Fábry

  29. Probability density function – varies in time Increasing Level of Mathematical Difficulty Deterministic Probabilistic Static Dynamic Stationary Nonstationary Probability density function – unchanhged over time Rate of demand - known with certainty - not constant Rate of demand - known with certainty - constant Inventory Models Demand Classification Demand ___________________________________________________________________________ Operations Research  Jan Fábry

  30. Inventory Models Deterministic Models • Basic economic order quantity model (EOQ model) • EOQ model with back orders allowed (with planned shortages) • Economic production lot size model • EOQ model with quantity discounts ___________________________________________________________________________ Operations Research  Jan Fábry