An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Roll the Dice with Confidence:Play to Win By Bill Carswell Adjunct Professor Embry Riddle Aeronautical University

  2. Introduction • Schedule Risk Assessments (SRA): • Provides confidence levels for meeting schedule and budget targets • Identifies highest risk activities in the schedule and the budget

  3. SRA and Government Contracting • SRA is now required on Earned Value Management programs

  4. Integrated Program Management Report (IPMR) Implementation Guide 2.3.7.6: SRA… is a proven risk reduction scheduling practice. 2.3.7.6.1: The SRA employs software that uses Monte Carlo simulations…

  5. Integrated Program Management Report (IPMR) Implementation Guide 1.2 SRA is reported as part of Format 5

  6. Benefit to You “What distinguishes you as a contractor to the government is your ability to reduce their RISK” Dr. Marvin Carroll President/CEO Tec-Masters

  7. Sources of Software(MSProject Add-Ins) • Risky Project: Intaver Institute • Full Monte: Barbecana • @Risk: Palisade • Crystal Ball: Oracle • Acumen Risk: Deltek • Risk Analysis: Primavera • Risk+

  8. How It Works • SRA uses “Monte Carlo” (MC) method • 3-point estimates establish a range of possible activity durations (uncertainty) • MC “rolls the dice” to pick a duration for each schedule activity, independently • Evaluates schedule with “random” activity durations, then does it all again…10,000 times.

  9. Sample Results • Original Schedule • Duration: 199 days • Finish: 9/4/12 • SRA Results (see next two slides) • 9/4/12: 30% Probability • 9/6/12: 50% Probability • 9/11/12: 80% Probability

  10. Histogram Results

  11. Tornado Diagram Results

  12. Success Factors: Effective SRA Requires • Complete Schedule Logic: Fully sequenced with predecessors and successors • Good 3-point duration estimates • Limited number of date constraints • Fully resourced for budget analysis

  13. Bicycle Example

  14. Thank You! PM Planning is a “Pay now or pay much more later” business. Bill Carswell, Ph.D., PMPcarswell@hiwaay.net256-679-2276 www.linkedin.com/in/spacien/Please feel free to connect!