1 / 18

P25 Digital Statewide Public Safety Radio System

P25 Digital Statewide Public Safety Radio System. Project Planning & Implementation Certification Request Presented by: Michael Rohrbacher October 24, 2019. Agenda. Project Overview Solution Design Funding & Certification Request. Project Overview. P25 Project Overview.

benjamin
Télécharger la présentation

P25 Digital Statewide Public Safety Radio System

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. P25 Digital Statewide Public Safety Radio System Project Planning & Implementation Certification Request Presented by: Michael Rohrbacher October 24, 2019

  2. Agenda • Project Overview • Solution Design • Funding & Certification Request

  3. Project Overview

  4. P25 Project Overview • Modernize existing Public Safety Land Mobile Radio (PSLMR) system to: • Provide a modern, feature-rich system based on current standards • Improve service quality, coverage, capacity and interoperability for State and local agencies • Create seamless state-wide system to support first responders • Solution will comply with Project 25 (P25) standards for digital technology • New system will be available to local agencies who want to participate in these service offerings

  5. Scope • Scope • Full project scope for state-wide implementation is unchanged and dependent upon funding. • Current Phase: Deploy P25 digital radio system in City of Albuquerque, Bernalillo County (ABQ/BC) and at Spaceport America (SPA) • 10 new trunked radio sites, core enhancements • New microwave backhaul • Radio, consoles, equipment and training for SPA

  6. State wide deployment • Overall Strategy (Phases) • Actual scope per phase will be determined by available funding and local participation; will create detailed next-phase plan as funding secured • Tentative overall plan: • Statewide major roadway (I-25) coverage deployment and subscriber replacement • Statewide minor roadway coverage deployment 1 and subscriber replacement • Statewide minor roadway coverage deployment 2 and subscriber replacement • Statewide final coverage enhancement and portable coverage in selected areas • Currently in discussions with potential local partners: • Valencia County • Sandoval County • Eddy County – decided to participate as of 10.14.2019 • San Miguel County • City of Lordsburg / Hidalgo County • Continuing outreach to local agencies

  7. Accomplishments to Date • Work toward P25 solution began as part of DoIT’s ongoing work to sustain and improve PSLMR • Accomplishments include: • Installed primary and redundant system core • Installed 8 digital trunking sites in metro area and Roswell • Purchased 250 subscriber units and accessories • Engaged in extensive outreach and information campaigns related to the P25 effort • Designed state-wide deployment plan • Designed ABQ/BC expansion • Designed SPA expansion • Obtained Technical Architecture Review Committee (TARC) approval for segments I and II • Obtained IV&V waiver • Executed contract with Motorola for initial implementation • Drafted interagency agreements with ABQ/BC and SPA • Began work on provisional service rates • Initiated P25 Project Advisory Committee and PSR Operations Working Group • Developed project management plan • Held design review with stakeholders

  8. Timeline

  9. Solution Design

  10. P25 Core Technology Primary Core • Hardware is fully redundant • Essentially a big packet switch • Uses various servers and virtual servers for management and administration • Majority of components are Commercial Off The Shelf (COTS) Oso Grande Geo-Redundant Core

  11. Architecture Overview Other Dispatch Centers City / County Dispatch Centers

  12. Mobile Radio Coverage (Bernalillo County)

  13. Portable Radio Coverage (Bernalillo County)

  14. Funding & Certification Request

  15. Funding & Certification History • Certification history: • Initiation Certification: September 27, 2018 - $10 million • Change Request: June 26, 2019 - $0

  16. Planned Contracts

  17. Certification Request • Requesting combined Planning and Implementation certification for current phase of P25 Project (Albuquerque, Bernalillo County, Spaceport Expansion), and certification of an additional $11,300,704 for this work

  18. Questions

More Related