1 / 14

The CSO Abatement Project

The CSO Abatement Project. Presented by: Paul Nordstrom Director of Operations and Engineering. CSO CONTROL PROGRAM. To be completed in three phases Phase 1 under construction and scheduled for completion in October 2008. Construction cost = $320 million

bernad
Télécharger la présentation

The CSO Abatement Project

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The CSO Abatement Project Presented by: Paul Nordstrom Director of Operations and Engineering

  2. CSO CONTROL PROGRAM • To be completed in three phases • Phase 1 under construction and scheduled for completion in October 2008. Construction cost = $320 million • Phase 2 design to be initiated in August 2007

  3. GENERAL LOCATION PLAN

  4. COMBINED SEWAGE OVERFLOW- DIVERSION AND STORAGE

  5. SITE S1 CONFIGURATION OF PUMP STATION OPERATING FACILITIES

  6. PERIOD: COMPLETION OF C6 TUNNEL LINING TO COMPLETION OF C6 CONTRACT CONTRACT C6 CONTRACT C14 S1 CONSTRUCTION SITE STAGING

  7. FOUNDRY WORK SHAFT/ WOONASQUATUCKET INTERCEPTOR DROP SHAFT

  8. Field’s Point WWTF Design • Average Daily Flow – 45 MGD • Design Capacity – 65 MGD • Peak Secondary Flow Capacity – 77 MGD • Wet Weather Treatment Capacity (Primary Treatment and Disinfection) – 123 MGD

More Related