Alpha Magnetic Spectrometer – 02 RID Overview & Disposition

Alpha Magnetic Spectrometer – 02 RID Overview & Disposition. Re-baselining Outbrief July 15, 2004 Trent Martin. Documents for Review. http://www4.jsc.nasa.gov/eaprojects/ea-projects/flightgfe/ams_02/html/ams_02.htm. Other Items for Review.

bernad
Télécharger la présentation

Alpha Magnetic Spectrometer – 02 RID Overview & Disposition

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Alpha Magnetic Spectrometer – 02 RID Overview & Disposition Re-baselining Outbrief July 15, 2004 Trent Martin

  2. Documents for Review http://www4.jsc.nasa.gov/eaprojects/ea-projects/flightgfe/ams_02/html/ams_02.htm AMS Re-Baselining RIDs 15-July-2004

  3. Other Items for Review AMS Re-Baselining RIDs 15-July-2004

  4. Review Team Status as of July 15, 2004 – 84 Total RIDs PA – Pending Action

  5. RID Statistics Red – Open Yellow – Open pending document update Green - closed AMS Re-Baselining RIDs 15-July-2004

  6. Major RID Findings • Project Plan editorial comments, clarifications and reorganization • PTRS editorial comments and clarifications • Major decision to pull verification matrix out of PTRS and write the V&VD now • ICD & SVP editorial comments and clarifications AMS Re-Baselining RIDs 15-July-2004

  7. RID Statistics • 3 Open • RID 19 – Remove LMSO from all documents • RID 75 – Add 2nd ACOP • RID 77 – Modify AMS Payload Goals • 13 Open Pending Action • RIDs 1,52,53 – Updates to SVP • RIDs 3,66,67,68,78,79,81,82 – PIH to AMS ICD or VC ICD • RIDs 61,65 - New V&VD • 68 Closed • RID 76 – Many updates to Project Plan AMS Re-Baselining RIDs 15-July-2004

  8. CDR RID Summary • Had 38 open RIDs at the start of the rebaselining review • 21 Open RIDs • Majority are open pending work that was either delayed due to lack of funding or are part of the standard process for later reviews (FSR II and III) • 17 Closed RIDs • Mostly duplicated by Rebaselining RIDs or superceded by new document revisions • Will bring closure plan back to first CCB (August) AMS Re-Baselining RIDs 15-July-2004