February 12th, 2007 Purpose: To implement a fastest route algorithm in a GPS enabled vehicle.

Status Report #3 GPS-Navigated Autonomous Vehicle. Prepared for: August Allo Department of Electrical Engineering University of Texas at San Antonio. Prepared by Design Group 8: Brendon Balouch Vernal Garcia Brian Gonzalez Kim Pham. February 12th, 2007 Purpose:

bess
Télécharger la présentation

February 12th, 2007 Purpose: To implement a fastest route algorithm in a GPS enabled vehicle.

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Status Report #3GPS-Navigated Autonomous Vehicle Prepared for: August Allo Department of Electrical Engineering University of Texas at San Antonio Prepared by Design Group 8: Brendon Balouch Vernal Garcia Brian Gonzalez Kim Pham February 12th, 2007 Purpose: To implement a fastest route algorithm in a GPS enabled vehicle.

  2. Overall Need: Autonomous path following via GPS. • Project Milestones: • Establish communication between GPS and microprocessor • Write our fastest route algorithm. • Integrate all pieces into a single package

  3. Task Completions • SIRF binary data instead of GPS NMEA encoded messages • added a diagnostics menu • GPS coordinates will now use XYZ Cartesian geodetic coordinates • Steering control circuit • Drive train control circuit

  4. Task Completion Dates • PWM Motor Driver Schematic • February 23, 2007 • H-Bridge Steering Controller Schematic • February 23, 2007

  5. Upcoming Tasks • Fastest route algorithm • Programming of processor to support peripheral devices • Part: • Magnetometer

  6. Upcoming Task Completion Dates • Fastest Route Algorithm • March 10, 2007 • Project Synergy • April 15, 2007