1 / 26

Lessons Learned from AIE Surveys Performed in Summer 1999

Lessons Learned from AIE Surveys Performed in Summer 1999. SERC System Operators Conference Spring - 2000. 1999 AIE Surveys. What is an AIE Survey? When are AIE Surveys performed? What lessons were learned from the AIE Surveys?. 1999 AIE Surveys. What is an AIE Survey?

bess
Télécharger la présentation

Lessons Learned from AIE Surveys Performed in Summer 1999

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Lessons Learned fromAIE Surveys Performed in Summer 1999 SERC System Operators Conference Spring - 2000

  2. 1999 AIE Surveys • What is an AIE Survey? • When are AIE Surveys performed? • What lessons were learned from the AIE Surveys?

  3. 1999 AIE Surveys • What is an AIE Survey? • When are AIE Surveys performed? • What lessons were learned from the AIE Surveys?

  4. AIE Survey • An AIE survey is a means of identifying control areas that operate with prolonged generation/load imbalance. • All control areas within an Interconnection must participate in AIE surveys.

  5. AIE Survey Authorization

  6. AIE Survey Training Document

  7. AIE Survey Form

  8. 1999 AIE Surveys • What is an AIE Survey? • When are AIE Surveys performed? • What lessons were learned from the AIE Surveys?

  9. Calling AIE Surveys • AIE Surveys are called by the Chairman of the Performance Subcommittee • Performance Subcommittee established informal criteria for calling AIE Surveys if the daily Epsilon 1 (an indication of frequency error) is greater than 16.0 milliHertz

  10. Bad Frequency Days

  11. Record Bad Frequency2/22/99

  12. Record Bad Frequency2/23/99

  13. Record Bad Frequency2/29/99

  14. 1999 AIE Surveys • What is an AIE Survey? • When are AIE Surveys performed? • What lessons were learned from the AIE Surveys?

  15. Bad Performers Discussed in presentation.

  16. Cinergy Corporation

  17. ECARJudgementof Cinergy • … CINergy used the Eastern Interconnection as a supplemental resource without regard to the reliability or integrity of the system or the well being of the many users of the system. • … CINergy’s interchange performance on July 22, 23, and 29 was the major contributor to the low frequency experienced in the Eastern Interconnection • CINergy’s blatant disregard for NERC policy and ECAR documents during this period jeopardized the reliability of the Eastern Interconnection especially in its ability to respond to additional contingencies. • .… A follow-on ECAR investigation … led the ECAR Executive Board to conclude that CINergy knowingly disregarded the clearly defined operating requirements of NERC Policy 5 and ECAR Documents 2 and 3 during the AIE survey period.

  18. ECAR Resolution

  19. Entergy

  20. Entergy July 22, 1999 • System Load was higher then expected • Unit Outages : • Baxter Wilson 1(515 MW), • Sterlington 6 (225 MW), • Lake Catherine 2 (30 MW) • Several Units were derated • Approximately 250 MW of purchased capacity recalled • Corrective Actions Taken : • Curtailment of curtailable industrial customers • Curtailment of capacity sales • bought emergency power

  21. Entergy July 23, 1999 • Unit Outages : • Baxter Wilson 1 (515 MW) • White Bluff 1 (815 MW), • Willow Glenn 5 (550 MW) • 500 MW derated generating capacity • Transaction Information : • Lost 500 MW of SPP Emergency Assist • Lost 400 MW of pre-scheduled purchase power • Hourly purchase power availability was minimal • Corrective Actions Taken : • curtailed all Interruptible/Curtailable Retail load • curtailed 900 MW of firm load at 2:42 PM.

  22. Entergy Conclusions • “If we had to do it again, we wouldn’t.” -Tim Ponseti • Lessons Learned : • Timing is critical • Call for emergency assistence • Call for curtailable load • Additional generation has been taken out of mothballs to provide additional generation

  23. DOE Report

  24. TVA • July 29 - TVA experienced a telemetry failure on one phase of a 500 kV transmission line • This caused an offset of 300+ MW in real time ACE used for control • The failure was not detected and/or corrected during the AIE Survey period

  25. Lessons Learned formTie Line Metering Error • Sudden spikes of ACE are not always false- telemetry • All tie line meters need voltage alarms - phase to phase • Finding erroneous errors are very difficult without hard copy charts • All tie line meters should have reasonability alarms • All control areas should have at minimum trend charts for net schedules and actuals

  26. Questions?

More Related