Presentation to: Seminar on Progress of Rural Water Programme 2006 Shamrock Lodge Hotel Athlone

National Report to EU Commission on measures to achieve compliance with the EU Drinking Water Directive. Presentation to: Seminar on Progress of Rural Water Programme 2006 Shamrock Lodge Hotel Athlone 8 h June 2006. BACKGROUND. European Court of Justice Ruling 2002

betsy
Télécharger la présentation

Presentation to: Seminar on Progress of Rural Water Programme 2006 Shamrock Lodge Hotel Athlone

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. National Report to EU Commission on measures to achievecompliance with the EU Drinking Water Directive Presentation to: Seminar on Progress of Rural Water Programme 2006 Shamrock Lodge Hotel Athlone 8h June 2006

  2. BACKGROUND • European Court of Justice Ruling 2002 • Ireland in breech of obligations under Drinking Water Directive • Annex 14 List • 819 Group Water Schemes non compliant with bacteriological standards • EU Commission: Schemes < 50 persons excluded from Action Plan • 453 schemes serving > 50 persons or having a commercial supply element • Additional Schemes • 274 private schemes fall within remit of DWD

  3. LIAISON WITH LOCAL AUTHORITIES

  4. SCHEME REPORT TEMPLATE

  5. REPORT COMPILATION by • Co-ordinate information received from Consultants • Analyse and evaluate findings • 3-Layered Report • Individual Scheme Report • County Report • Annex 14 Schemes • Additional Schemes identified during the NRWMP • All Schemes • National Report • Annex 14 Schemes • Additional Schemes identified during the NRWMP • All Schemes • MapInfo Drawings • National basis • County by County basis

  6. NATIONAL REPORT • Sources & Ownership • Taken over by Local Authority • Metered supply from public scheme • Private source • Bacteriological Compliance of Schemes • Scheme basis • Consumer basis • Treatment Solutions Identified by L.A. • Realisation of Identified Treatment Solution • MapInfo Drawings

  7. SOURCES & OWNERSHIP (National Level)

  8. SOURCES & OWNERSHIP (National Level) 700 581 600 500 352 400 No of Schemes 300 229 200 92 61 54 100 40 31 14 0 PWS Public GWS Private GWS All Schemes Annex 14 Additional Schemes

  9. MICROBIOLOGICAL RESULTS - Scheme Compliance Schemes at National Level

  10. MICROBIOLOGICAL RESULTS - Overall Scheme Compliance All Schemes (727) No Yes 47% 53% Non-Annex 14 Schemes (274) Annex 14 Schemes (453) No No Yes Yes 50% 43% 57% 50%

  11. MICROBIOLOGICAL RESULTS - Domestic Consumer Compliance All Schemes (91,776) No Yes 47% 53% Non-Annex 14 Schemes (23,840) Annex 14 Schemes (67,936)

  12. MICROBIOLOGICAL RESULTS - Private Scheme Compliance All Schemes (581 of 727) Non-Annex 14 Schemes (229 of 274) Annex 14 Schemes (352 of 453)

  13. SOLUTIONS IDENTIFIED (as per DoEHLG Questionnaire) • DBO Treatment • Non DBO Treatment • Metered Connection of GWS to Public Main • Takeover of GWS by Local Authority • Disinfection/Sterilisation • Public source to be maintained by Local Authority

  14. SOLUTIONS IDENTIFIED (Nationally on a scheme basis) All Schemes (727) Annex 14 Schemes (453) 3% 2% 17% 17% 36% 7% 44% 8% 8% 16% 20% 22% Non Annex 14 Schemes (274) DBO Treatment 5% 16% Non-DBOTreatment 22% Connect to Public Supply 10% Takeover by Local Authority Disinfection/ Sterilisation 16% Scheme with Public Source 31%

  15. SOLUTIONS IDENTIFIED (Geographic spread of scheme solutions) IRELANDAll Schemes Solutions Identified by L.A. Solutions Identified by L.A. DBO Treatment DBO Treatment Non DBO Treatment Non DBO Treatment Connect to Public Main Connect to Public Main Takeover by Local Authority Takeover by Local Authority Disinfection/Sterilisation Disinfection/Sterilisation Scheme with Public Source Scheme with Public Source

  16. SOLUTIONS IDENTIFIED (Geographic spread of scheme solutions) IRELANDAnnex 14 Schemes (453) IRELANDAdditional Non-Annex 14 Schemes (274) Solutions Identified by L.A. DBO Treatment DBO Treatment Non DBO Treatment Connect to Public Main Takeover by Local Authority Disinfection/Sterilisation Scheme with Public Source

  17. SOLUTIONS IDENTIFIED (As % of domestic connections served) All Schemes (91,776) DBO Treatment Non-DBOTreatment Connect to Public Supply Takeover by Local Authority Disinfection/ Sterilisation Scheme with Public Source Non Annex 14 Schemes (23,840) Annex 14 Schemes (67,936)

  18. SOLUTIONS IDENTIFIED (Nationally for Private Schemes) All Schemes (581) DBO Treatment Non-DBOTreatment Connect to Public Supply Takeover by Local Authority Disinfection/ Sterilisation Scheme with Public Source Non Annex 14 Schemes (229) Annex 14 Schemes (352)

  19. STATUS OF IDENTIFIED SOLUTIONS Status of Scheme Solutions by percentage nationally All Schemes (727) Non-Annex 14 Schemes (274) Annex 14 Schemes (453) Status of Private Scheme Solutions by percentage nationally Non-Annex 14 Schemes (229) All Schemes (581) Annex 14 Schemes (352)

  20. STATUS OF IDENTIFIED SOLUTIONS Status of Solutions by percentage of domestic connections nationally All Schemes (91,776) Non-Annex 14 Schemes (23,840) Annex 14 Schemes (67,936)

  21. TREATMENT SOLUTIONS FOR PRIVATE SOURCES Schemes for DBO Treatment All Schemes (259) Non-Annex 14 Schemes (60) Annex 14 Schemes (199)

  22. TREATMENT SOLUTIONS FOR PRIVATE SOURCES Schemes to be connected to Public Mains All Schemes (122) Non-Annex 14 Schemes (44) Annex 14 Schemes (78)

  23. TREATMENT SOLUTIONS FOR PRIVATE SOURCES Schemes to be taken over by Local Authority All Schemes (60) Non-Annex 14 Schemes (28) Annex 14 Schemes (32)

  24. Solutions Identified by L.A. Solutions Identified by L.A. (70) DBO Treatment DBO Treatment Non DBO Treatment Non DBO Treatment (2) Connect to Public Main Connect to Public Main (25) Takeover by Local Authority Takeover by Local Authority (23) Disinfection/Sterilisation Disinfection/Sterilisation (7) Scheme with Public Source Scheme with Public Source (51) (178)

  25. Annex 14 Schemes Additional Non-Compliant Schemes

  26. Bacteriological Results in Compliance Yes No

  27. Label by ID Number

  28. CONCLUSIONS • 18 Counties in Annex 14 List • Schemes which now come under the remit of the DWD are identified in 26 Local Authorities • Sampling from 53% of Schemes comply with DWD while 55% of 91,776 domestic connections on 727 schemes are compliant • Only 45% of schemes with Private sources are compliant • Of 91,776 domestic connections on GWS nationwide • 38% of treatment solutions are complete • 45% of treatment solutions are underway • 17% are still in planning • DBO solutions are much further advanced than other solutions with 93% of scheme solutions complete or underway • Only 27% of solutions involving connection to public mains are complete or underway