An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BEVERLY HILLS APOSTOLIC CHRISTIAN CHURCH SUNDAY SCHOOL & FELLOWSHIP AREA

  2. Costs BUILDING COST $280,000 PARKING LOT COST $80,000 SUBTOTAL $360,000 10% CONTINGENCY $36,000 TOTAL$396,000 BEVERLY HILLS APOSTOLIC CHRISTIAN CHURCH SUNDAY SCHOOL & FELLOWSHIP AREA

  3. Cost Basis • includes demo of existing S.S. building • includes some sitework around new building • assumes wood framed building, with brick exterior • assumes nice level of finish, not real cheap, not real expensive • assumes commercial kitchen requirements • some ceramic floors: toilets and entry • lay-in ceiling • $4300 for appliances BEVERLY HILLS APOSTOLIC CHRISTIAN CHURCH SUNDAY SCHOOL & FELLOWSHIP AREA

  4. VOLUNTEER ASSUMPTIONS • rough carpentry labor • painting • finish carpentry • cleaning • general labor • OTHER POTENTIAL AREAS • electrical • plumbing • tile work • ceilings BEVERLY HILLS APOSTOLIC CHRISTIAN CHURCH SUNDAY SCHOOL & FELLOWSHIP AREA

  5. STATISTICS EXISTING CONDITION BEVERLY HILLS APOSTOLIC CHRISTIAN CHURCH SUNDAY SCHOOL & FELLOWSHIP AREA

  6. STATISTICS PROPOSED PROJECT BEVERLY HILLS APOSTOLIC CHRISTIAN CHURCH SUNDAY SCHOOL & FELLOWSHIP AREA

  7. BABY ROOM TOILET ROOMS FOYER CLASSROOMS OFFICE FURNACE CLASSROOMS EATING AREA KITCHEN SINGING TOILET PANTRY BEVERLY HILLS APOSTOLIC CHRISTIAN CHURCH SUNDAY SCHOOL & FELLOWSHIP AREA

  8. BEVERLY HILLS APOSTOLIC CHRISTIAN CHURCH SUNDAY SCHOOL & FELLOWSHIP AREA

  9. SANCTUARY FOYER • GENERAL DESIGN ASSUMPTIONS: • Covered main entry from parking area • secondary/ service entry from parking area • ability to expand to the north a little • create large flexible space rather than multiple small ones BEVERLY HILLS APOSTOLIC CHRISTIAN CHURCH renovation February 26th, 2006

  10. NOISE NOISE BARRIER SANCTUARY FOYER NOISE BARRIER • ISSUES (not in order of importance): • Noise • Safety • Current and future flexibility • Cost BEVERLY HILLS APOSTOLIC CHRISTIAN CHURCH renovation February 26th, 2006

  11. KITCHEN • ISSUES (not in order of importance): • Noise • Safety • Current and future flexibility • Cost BEVERLY HILLS APOSTOLIC CHRISTIAN CHURCH renovation February 26th, 2006

  12. ONE OPTION TO DEAL WITH CRAFTS STORAGE • ADD BASE CABINETS, COUNTERTOP AND UPPER CABINETS ON OPEN AREA SIDE OF “STORAGE” • STORAGE SPACE GETS A LITTLE SMALLER BEVERLY HILLS APOSTOLIC CHRISTIAN CHURCH renovation February 26th, 2006

  13. ANOTHER OPTION TO DEAL WITH CRAFTS STORAGE • GROW A CLASSROOM AND PUT FULL SIZE STORAGE UNITS IN ROOM – IT WOULD SERVE AS CRAFT ROOM • STORAGE SPACE GETS A LITTLE SMALLER BEVERLY HILLS APOSTOLIC CHRISTIAN CHURCH renovation February 26th, 2006

  14. BEVERLY HILLS APOSTOLIC CHRISTIAN CHURCH renovation February 26th, 2006

  15. Next Steps • Meet with city building official to determine his wants • Hire surveyor and civil engineer for site drawings • Submit for site plan approval • Submit for Land use approval • Finish construction Drawings • Bid out subcontracts • Start Construction BEVERLY HILLS APOSTOLIC CHRISTIAN CHURCH SUNDAY SCHOOL & FELLOWSHIP AREA

  16. TIMEFRAME • Do we want to have all the money in hand before we start or are we willing to start the process with what we have? • Building Committee Recommendation: • Start with the process now • Hire civil engineer, surveyor • Proceed with plans, talk with city • Keep fundraising • Send out notes asking for pledges BEVERLY HILLS APOSTOLIC CHRISTIAN CHURCH SUNDAY SCHOOL & FELLOWSHIP AREA