WidT Test strategy v0.9, June 30th 2014
IntroductionProject context • Project plan and schedule are available [concept version] • De-branding is finished • Migration to “new” Network Operating Centre is finished • Optimisation WidT • Fair Use Policy, Caching • Improving existing services • Authentication, Security, Portal Page [including CMS] • Adding new services • Registering, Local content • The Test Strategy needs to ensure that the implemented changes and additions are validated WidT
StakeholdersWho is involved in this project? • Frank en Miryam : Owner of the service • Erik : Senior User • Kitty : Contract & Supplier Management • Laura : Legal • Eelco : Business Consultant • Hans : Program Architect • Pieter : Project Architect • Patrick : Technical Architect • Caroline : Information Analyst • Niels van Riel: Operations • Bill Gertz: ICT Security Officer • Patrick : Senior Supplier • Han : Network Operating Centre • Paul : Project Manager • Bart : Program Manager • Ruud : Test Manager WidT
Product Risk Analysis [PRISMA] • Quadrant I: • Security en Performance • Quadrant II: • No items! • Quadrant III: • Internet access, Providing information, Authentication, Portal Page & Confirmation Page, ISP, Optimisation, Minimisation • Quadrant IV • User Friendliness, Additional services, CMS, Behaviour “Online & Offline” Remarkable:Overall a relative low chance of failure WidT
Test objectivesShow that… • security requirements are met [12]!! Need to be defined/detailed • performance is acceptable [13]!! Need to be defined/detailed • it is and remains possible to access the internet through “WidT” [1, 8, 11] • provided information is actual, accurate and unambiguous [1, 9, 10, 11] • the user can log on to the system and/of is authenticated in the correct manner [3, 11]!! Need to be defined/detailed • the technical implementation meets the requirements set to an ISP [4]!! Need to be defined/detailed • optimisation of the data throughput without impacting the “essence” (internet access, standard information) [5]!! Need to be defined/detailed • minimising the data usage without impacting the “essence” (internet access, standard information) (internet access, standard information) [6]!! Need to be defined/detailed • Changes can be performed through the CMS [2]!! is separate RFC, unknown delivery date • Added services “work as designed” and are “fit for purpose]”!! Need to be defined/detailed WidT
Test strategy (1/2)What approach is chosen to achieve the objectives? Security • Approach is chosen and tuned together with the ICT security officers • Directly depends on the requirements and chosen implementation • Static [audits, reviews] • Dynamic [e.g. penetration testing] Performance • Approach is chosen and tuned together with the IT-OPS performance experts • Directly depends on the requirements • Implicit [e.g. monitoring in production] • Explicit [e.g. performance test in production]!! performance testing in testlab has no added value!! Internet Access and providing information • Regression test based on existing test script performed in testlab • Simulate End-to-End chain wrt providing information in testlab • CMS [Portal Page, Confirmation Page] • Standard information WidT
Test strategy (2/2)What approach is chosen to achieve the objectives? ISP functionality • Static [audits, reviews] • Dynamic [e.g. whitelisting, blacklisting] Optimisation & minimisation of data throughput • Directly depends on the requirements and chosen implementation • Static [review implemented measures] • Dynamic [measurements in testlab and monitoring in production] CMS functionality • Regression test based on existing test script performed in testlab • Simulate End-to-End chain wrt providing information in testlab • Additional test script focused on the [Portal Page, Confirmation Page] Additional services • Directly depends on the requirements and chosen implementation • To be defined WidT
Test LevelsWhich tests will be performed? • Supplier(s) • Focus on “Works as designed”Depending on size & impact: UT, UIT, ST, SIT!!: Suppliers need to be contacted to arrange this !! • Business • Focus on “Fit for purpose“Depending on size & impact: FAT, UAT, PAT, E2E-test • Focus on “meeting the requirements”Audit & review WidT
Test environment • Supplier • “Own” environment • “Own” testlab [e.g. Testlab Haarlem] • NOC • Testlab [Utrecht or Amersfoort] • Business • NOC • Testlab [Utrecht or Amersfoort] • “Pilot” • Production WidT
Go/No-Go WidT
Test schedule & activitiesWhen to do what (or what to do when)? Planning test activities • Generic: Process focused on the ability to quickly respond • Specific: When the project decides what to do next • Optional: Plan and agree on cooperation with supplier and review Preparation& specification • Generic: Claim test environment(s), prepare regression test(s) • Specific: When requirements and deliverables are defined • Optional: Monitor supplier Execution • Generic: Check delivery, execute “smoke-test” • Specific: What is prepared and specified Sign off • Reporting: GO/NO-GO advice, test report, testware WidT
Test basisWhich information is relevant for testing? Test basis • “ist”: Not documented, regression test is leading • “soll”: Changed and added requiremenst are described in RFC Presentations Use Cases Requirements should be documented in a standard way WidT
Issues • Logged in JIRA • Monitored by the test manager WidT
Reporting Progress • Generic: Weakly during the team meeting • Specific: From initiation until deployment Report per stage • Supplier: Delivery includes a test report and remaining issue log • Test manager: Go/No-go advice Final report • Test manager: Final report, including testware WidT
Test resources • Ruud : Test manager Test on behalf of the business • Niels : Test on behalf of Operations • Jan: Test analyst at the testlab • Caroline : Support wrt designs • Supplier: Support wrt development • Operations: Support Performance Testing • Security Officer: Support Security Testing WidT