Chapter 17: Learning Objectives. You should be able to: Discuss the behavioral aspects of projects in terms of project personnel and the project manager Explain the nature and importance of a work breakdown structure in project management Give a general description of PERT/CPM techniques

1 / 72

Télécharger la présentation

Chapter 17: Learning Objectives

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript

Playing audio...

  1. Chapter 17: Learning Objectives • You should be able to: • Discuss the behavioral aspects of projects in terms of project personnel and the project manager • Explain the nature and importance of a work breakdown structure in project management • Give a general description of PERT/CPM techniques • Construct simple network diagrams • List the kinds of information that a PERT or CPM analysis can provide • Analyze networks with deterministic times • Analyze networks with probabilistic times • Describe activity ‘crashing’ and solve typical problems 17-1

  2. Projects • Projects • Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame • Examples: • The Olympic Games • Producing a movie • Software development • Product development • ERP implementation 17-2

  3. Project Life Cycle 17-3

  4. Work Breakdown Structure (WBS) • WBS • A hierarchical listing of what must be done during a project • Establishes a logical framework for identifying the required activities for the project • Identify the major elements of the project • Identify the major supporting activities for each of the major elements • Break down each major supporting activity into a list of the activities that will be needed to accomplish it 17-4

  5. WBS 17-5

  6. Gantt Chart 17-6

  7. PERT and CPM • PERT (program evaluation and review technique) and CPM (critical path method) are two techniques used to manage large-scale projects • By using PERT or CPM Managers can obtain: • A graphical display of project activities • An estimate of how long the project will take • An indication of which activities are most critical to timely project completion • An indication of how long any activity can be delayed without delaying the project 17-7

  8. Network Diagram • Network diagram • Diagram of project activities that shows sequential relationships by use of arrows and nodes • Activity on arrow (AOA) • Network diagram convention in which arrows designate activities • Activity on node (AON) • Network convention in which nodes designate activities • Activities • Project steps that consume resources and/or time • Events • The starting and finishing of activities 17-8

  9. AON Convention Activity on Activity Meaning Node (AON) A C (a) B A comes before B, which comes before C. A A and B must both be completed before C can start. (b) C B B B and C cannot begin until A is completed. A (c) C 17-9

  10. A C B D A C B D AON Convention Activity on Activity Meaning Node (AON) C and D cannot begin until both A and B are completed. (d) C cannot begin until both A and B are completed; D cannot begin until B is completed. A dummy activity is introduced in AOA. (e) 17-10

  11. B A C D AON Convention Activity on Activity Meaning Node (AON) B and C cannot begin until A is completed. D cannot begin until both B and C are completed. A dummy activity is again introduced in AOA. (f) 17-11

  12. AON Example Project Activities and Predecessors 17-12

  13. Activity A (Build Internal Components) A Start Activity B (Modify Roof and Floor) B Start Activity AON Network 17-13

  14. Activity A Precedes Activity C A C Start B D Activities A and B Precede Activity D AON Network 17-14

  15. F A C E Start H B G D Arrows Show Precedence Relationships AON Network 17-15

  16. Deterministic Time Estimates • Deterministic • Time estimates that are fairly certain • Probabilistic • Time estimates that allow for variation 17-16

  17. Activity Description Time (weeks) A Build internal components 2 B Modify roof and floor 3 C Construct collection stack 2 D Pour concrete and install frame 4 E Build high-temperature burner 4 F Install pollution control system 3 G Install air pollution device 5 H Inspect and test 2 Total Time (weeks) 25 Determining Project Duration 17-17

  18. Determining the Project Duration Critical Path Critical path = Longest path A-C-E-G-H Project duration = 15 weeks 17-18

  19. Early Start, Early Finish • Finding ES and EF involves a forward pass through the network diagram • Early start (ES) • The earliest time an activity can start • Assumes all preceding activities start as early as possible • For nodes with one entering arrow • ES = EF of the entering arrow • For activities leaving nodes with multiple entering arrows • ES = the largest of the largest entering EF • Early finish (EF) • The earliest time an activity can finish • EF = ES + t 17-19

  20. Late Start, Late Finish • Finding LS and LF involves a backward pass through the network diagram • Late Start (LS) • The latest time the activity can start and not delay the project • The latest starting time for each activity is equal to its latest finishing time minus its expected duration: • LS = LF - t • Late Finish (LF) • The latest time the activity can finish and not delay the project • For nodes with one leaving arrow, LF for nodes entering that node equals the LS of the leaving arrow • For nodes with multiple leaving arrows, LF for arrows entering node equals the smallest of the leaving arrows 17-20

  21. Slack and the Critical Path • Slack can be computed one of two ways: • Slack = LS – ES • Slack = LF – EF • Critical path • The critical path is indicated by the activities with zero slack 17-21

  22. Activity Name or Symbol A Earliest Finish Earliest Start ES EF LS LF Latest Finish Latest Start 2 Activity Duration Determining the Project Schedule Perform a Critical Path Analysis 17-22

  23. Forward Pass Begin at starting event and work forward Earliest Start Time Rule: • If an activity has only a single immediate predecessor, its ES equals the EF of the predecessor • If an activity has multiple immediate predecessors, its ES is the maximum of all the EF values of its predecessors ES = Max {EF of all immediate predecessors} 17-23

  24. Forward Pass Begin at starting event and work forward Earliest Finish Time Rule: • The earliest finish time (EF) of an activity is the sum of its earliest start time (ES) and its activity time EF = ES + Activity time 17-24

  25. ES EF = ES + Activity time Start 0 0 0 Forward Pass 17-25

  26. EF of A = ES of A + 2 ESof A A 2 0 2 Start 0 0 0 Forward Pass 17-26

  27. EF of B = ES of B + 3 A 2 ESof B 0 2 0 3 Start 0 0 B 3 0 Forward Pass 17-27

  28. A 2 C 2 0 2 2 4 Start 0 0 0 B 3 0 3 Forward Pass 17-28

  29. A 2 C 2 0 2 2 4 Start 0 0 = Max (2, 3) D 4 0 3 B 3 0 3 Forward Pass 7 17-29

  30. A 2 C 2 0 2 2 4 Start 0 0 0 B 3 D 4 0 3 3 7 Forward Pass 17-30

  31. A 2 C 2 F 3 0 2 4 7 2 4 E 4 H 2 Start 0 0 4 8 13 15 0 B 3 D 4 G 5 0 3 3 7 8 13 Forward Pass 17-31

  32. Backward Pass Begin with the last event and work backwards Latest Finish Time Rule: • If an activity is an immediate predecessor for just a single activity, its LF equals the LS of the activity that immediately follows it • If an activity is an immediate predecessor to more than one activity, its LF is the minimum of all LS values of all activities that immediately follow it LF = Min {LS of all immediate following activities} 17-32

  33. Backward Pass Begin with the last event and work backwards Latest Start Time Rule: • The latest start time (LS) of an activity is the difference of its latest finish time (LF) and its activity time LS = LF – Activity time 17-33

  34. A 2 C 2 F 3 0 2 4 7 2 4 E 4 H 2 Start 0 0 4 8 13 15 13 15 0 LS = LF – Activity time B 3 D 4 G 5 0 3 3 7 8 13 LF = EF of Project Backward Pass 17-34

  35. A 2 C 2 F 3 0 2 4 7 2 4 10 13 E 4 H 2 Start 0 0 LF = Min(LS of following activity) 4 8 13 15 13 15 0 B 3 D 4 G 5 0 3 3 7 8 13 Backward Pass 17-35

  36. LF = Min(4, 10) A 2 C 2 F 3 0 2 4 7 2 4 2 4 10 13 E 4 H 2 Start 0 0 4 8 13 15 13 15 4 8 0 B 3 D 4 G 5 0 3 3 7 8 13 8 13 Backward Pass 17-36

  37. A 2 C 2 F 3 0 2 4 7 2 4 2 4 10 13 0 2 E 4 H 2 Start 0 0 4 8 13 15 13 15 0 0 4 8 0 B 3 D 4 G 5 0 3 3 7 8 13 4 8 8 13 1 4 Backward Pass 17-37

  38. Computing Slack Time After computing the ES, EF, LS, and LF times for all activities, compute the slack or free time for each activity • Slack is the length of time an activity can be delayed without delaying the entire project Slack = LS – ES or Slack = LF – EF 17-38

  39. Earliest Earliest Latest Latest On Start Finish Start Finish Slack Critical Activity ES EF LS LF LS – ES Path A 0 2 0 2 0 Yes B 0 3 1 4 1 No C 2 4 2 4 0 Yes D 3 7 4 8 1 No E 4 8 4 8 0 Yes F 4 7 10 13 6 No G 8 13 8 13 0 Yes H 13 15 13 15 0 Yes Computing Slack Time 17-39

  40. Using Slack Times • Knowledge of slack times provides managers with information for planning allocation of scarce resources • Control efforts will be directed toward those activities that might be most susceptible to delaying the project • Activity slack times are based on the assumption that all of the activities on the same path will be started as early as possible and not exceed their expected time • If two activities are on the same path and have the same slack, this will be the total slack available to both 17-40

  41. Probabilistic Time Estimates • The beta distribution is generally used to describe the inherent variability in time estimates • The probabilistic approach involves three time estimates: • Optimistic time, (to) • The length of time required under optimal conditions • Pessimistic time, (tp) • The length of time required under the worst conditions • Most likely time, (tm) • The most probable length of time required 17-41

  42. Probabilistic Time Estimates The expected time, te ,for an activity is a weighted average of the three time estimates: The expected duration of a path is equal to the sum of the expected times of the activities on that path: 17-42

  43. Determining Path Probabilities 17-43

  44. Project Completion Time • A project is not complete until all project activities are complete • It is risky to only consider the critical path when assessing the probability of completing a project within a specified time. • To determine the probability of completing the project within a particular time frame • Calculate the probability that each path in the project will be completed within the specified time • Multiply these probabilities • The result is the probability that the project will be completed within the specified time 17-44

  45. Probabilistic Time Estimates • The standard deviation of each activity’s time is estimated as one-sixth of the difference between the pessimistic and optimistic time estimates. The variance is the square of the standard deviation: • Standard deviation of the expected time for the path 17-45

  46. Most Expected Optimistic Likely Pessimistic Time Variance Activity totmtpt = (to+ 4tm+ tp)/6 [(tp– to)/6]2 A 1 2 3 2 4/36 B 2 3 4 3 4/36 C 1 2 3 2 4/36 D 2 4 6 4 16/36 E 1 4 7 4 36/36 F 1 2 9 3 64/36 G 3 4 11 5 64/36 H 1 2 3 2 4/36 Computing Variance 17-46

  47. Knowledge of Path Statistics • Knowledge of expected path times and their standard deviations enables managers to compute probabilistic estimates about project completion such as: • The probability that the project will be completed by a certain time • The probability that the project will take longer than its expected completion time 17-47

  48. s2 = Project variance = (variances of activities on the path) p Computing Variance Path variance is computed by summing the variances of activities on the path 17-48

  49. Variance of critical path s2 = 4/36 + 4/36 + 36/36 + 64/36 + 4/36 = 112/36 = 3.1111 Standard deviation of critical path sp = Variance of critical path = 3.1111 = 1.7638 weeks p Computing Variance 17-49

  50. Probability of Project Completion Note: • Total project completion times follow a normal probability distribution • Activity times are statistically independent 17-50