An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. COROT

  2. Main events from the last CW (Granada) • INSTRUMENT • The Baffle • The problem (eigen frequencies) is understood, thanks to a very strong involvement of ESA, CNES and CSL technical teams. • New design of the feet • Qualification is successful • Flight Model is already manufactured & under integration • Integration & Test of the Instrument Flight Model has started in CNES-Toulouse • Optical verification under progress • First « Image » made with the telescope • SATELLITE • Mechanical & Thermal analyses have some delay because of late inputs from the launcher • Critical Design Review under progress • Conflict of resources with the CALIPSO mission

  3. Main events from the last CW (Granada) • GROUND SEGMENT • Control Segment  nominal • Command & Control : under Integration test • Flight Dynamics : under interface tests • Mission Segment  some issues • Very tight schedule • Insufficient resources • SYSTEM & OPERATIONS • RIS (System Interfaces Review) • Successful • Main outcomes are • Conflicts of resources with the Calipso mission have to be closely managed • Exploitation Phase to be quickly assessed (tasks, responsibilities & resources • LAUNCHER contract has started with Arianespace & Starsem

  4. Main events from the last CW (Granada) • SYSTEM & OPERATIONS • Reinforcement of the Network of Ground Stations • Delay of the Brasilian Ground Station • Location Change from Natal to Alcantara • No progress of interface definition for the last 6 months • Discussions are slowly restarting • Search for alternatives • Use of the MOST ground stations is under discussion • Vienna ground station is the likely candidate

  5. Planning

  6. Milestones LAUNCH Flight Readiness Review Satellite Qualification Review Satellite I&T Readiness RPQT Satellite CDR April 2005 System PDR Oct 2003 System Interfaces Review March 2005 Satellite PDR Jan 2004 Instrument CDR May 2004

  7. Next 6 months roadmap • Delivery of the Flight Instrument • Delivery of the Flight Platform • Preparation & Start of the satellite assembly • Integration and test of the Ground Segment • Preparation of the System Tests • Preparation of operations • Prepration of the launch campaign • Ship & Shoot approach (~30 days) • Ground Stations • Secure the schedule the Alcantara ground station • Perform the compatibility tests with the (MOST) ground station in Vienna

  8. Start the thinking ofPost-Launch Activities • Flight Acceptance • At least 2 months • Development Expertise is required • Technical assessment • Trouble shooting • Exploitation • A minimal Development Expertise is to be maintained • Tasks and associated responsibilities are to be defined • Resources needed (incl.preparation of exploitation • Manpower • Money • Exploitation Cost sharing • A dedicated Steering Committee has to be organized

  9. Budget (qualitative) Status • Instrument expenses are under control (development is over) • Satellite • Overcosts are expected because of possible delays • System & Ground Segment • Launcher: nominal expenses • Control Centre : nominal expenses • Mission Centre : serious funding issues • The budget for Exploitation is not defined yet

  10. Synthesis & Conclusion • Technical issues • Normal work • Planning • The launch of Calipso mission is on the (Corot) critical path • Budget • To think of provision for shifts of planning • Mission Center (CMC) funding to be increased • Exploitation to be prepared • Organization • Funding and budget • Conclusion • Huge progress of the project, the dream is now reality • The COROT team is at full-speed • The count-down is still running • The COROT satellite is still planned to be launched by the 2006 summertime (NEXT YEAR)