RAPID ADVANCE DEVELOPMENT MONORAIL SYSTEM

RAPID ADVANCE DEVELOPMENT MONORAIL SYSTEM. Presentation for. ACARP ROADWAY DEVELOPMENT WORKSHOPS MARCH 2008. System Evolution. Commenced 1993. System Objectives. PRODUCTIVITY To improve development productivity To reduce manual handling To improve section support process requirements

bwelch
Télécharger la présentation

RAPID ADVANCE DEVELOPMENT MONORAIL SYSTEM

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. RAPID ADVANCE DEVELOPMENT MONORAIL SYSTEM Presentation for ACARP ROADWAY DEVELOPMENT WORKSHOPS MARCH 2008

  2. System Evolution Commenced 1993

  3. System Objectives • PRODUCTIVITY • To improve development productivity • To reduce manual handling • To improve section support process requirements • To eliminate potential Longwall outage due to lack of continuity or shortened blocks • SAFETY • To reduce injuries via manual handling • To reduce injuries through section congestion • To improve general section standards and subsequent improvement in morale. • To improve ventilation due to dedicated vent lines. • OVERALL COST BENEFITS • Improved productivity at face and support process • Overall better allocation of panel manning ie road cleaning etc. • Safety-related savings • Reduction in materials repair/replacement

  4. System Design Overview • THE DEVELOPMENT MONORAIL SYSTEM CONSISTS OF: • Inbye Services System • Secondary Ventilation System • Outbye Services Management System

  5. Monorail System Design

  6. TASKSTHAT ARE ELIMINATED& ADDITIONAL BENEFITS • Vent Tube Handling • Cable handling • MONORAIL VIDEO • Ancillary & operational equipment suspended on monorail • Driveage sequence animation • Roof bolts installed with miner mounted rigs and remain installed for Longwall retreat. • Rails can remain installed greatly reducing L/W Monorail relocation times. • Improved Ventilation due to single line. • Reduced requirement for LHD machines in panel.

  7. TASKSTHAT ARE ELIMINATED& ADDITIONAL BENEFITS • Vent Tube Handling • Cable handling • Monorail video • ANCILLARY & OPERATIONAL EQUIPMENT SUSPENDED ON MONORAIL • Driveage sequence animation • Roof bolts installed with miner mounted rigs and remain installed for Longwall retreat. • Rails can remain installed greatly reducing L/W Monorail relocation times. • Improved Ventilation due to single line. • Reduced requirement for LHD machines in panel.

  8. ANCILLARY EQUIPMENT

  9. TASKSTHAT ARE ELIMINATED& ADDITIONAL BENEFITS • Vent Tube Handling • Cable handling • Monorail video • Ancillary & operational equipment suspended on monorail • DRIVEAGE SEQUENCE ANIMATION • Roof bolts installed with miner mounted rigs and remain installed for Longwall retreat. • Rails can remain installed greatly reducing L/W Monorail relocation times. • Improved Ventilation due to single line. • Reduced requirement for LHD machines in panel.

  10. PLAY Next Stage

  11. PLAY Next Stage

  12. PLAY Next Stage

  13. PLAY Next Stage

  14. PLAY Next Stage

  15. PLAY Next Stage

  16. PLAY Continue

  17. TASKSTHAT ARE ELIMINATED& ADDITIONAL BENEFITS • Vent tube handling • Cable handling • Monorail video • Ancillary & operational equipment suspended on monorail • Driveage sequence animation • Roof bolts installed with miner mounted rigs and remain installed for Longwall retreat. • Rails can remain installed greatly reducing L/W Monorail relocation times. • Improved Ventilation due to single line. • Reduced requirement for LHD machines in panel.

  18. NewstanCase Study System first introduced to Newstan in MG22, 2005

  19. Realised operational savings per pillar (Newstan)

  20. Panel Advance Gains

  21. EQUIPMENT DAMAGED IN LAST PANEL FOLLOWING UPGRADE • 1 x 5m length of flexible duct • 1 x Miner cable, caught on Eimco • 1 x Miner Transition

  22. Safety Statistics - Newstan • Prior to implementation of monorail system, figures show that there were in excess of 10 medically treated and LTI injuries throughout panel duration of MG22. • Statistics have shown that during the development of MG23 there was a total of 3 minor injuries (non medically treated).

  23. System Comparisions at Newstan Target of 1000 Metres per month – Single Miner C/W Monorail. Single Miner unit c/w monorail equalled Tandem Mining unit production within 3 Months.

  24. Future for theDevelopment Monorail • Kestrel Coal, 2 complete systems currently being manufactured c/w 8.5km of rail. • Currently have Newstan system at Macquarie workshop being modified for Mandalong installation. • Oaky North Coalfinal stages of engineering sign off.

  25. RAPID ADVANCE DEVELOPMENT MONORAIL SYSTEM ACARP ROADWAY DEVELOPMENT WORKSHOPS MARCH 2008 Australian Mining Prospect Awards – Highly Commended Award 2006 Hunter Manufacturing Award – Innovation in Technology 2006