An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. District of Columbia Water and Sewer Authority George S. Hawkins, General Manager Briefing on: NORTHEAST BOUNDARY NEIGHBORHOOD PROTECTION PROJECT FIRST STREET TUNNEL Briefing for: Councilmember McDuffie Utility Coordination Meeting December 9, 2013

  2. Background Project Snapshot • Long Term Control Plan (LTCP) to: • Relieve flooding the Northeast Boundary Area • Control combined sewer overflows to: • Potomac River • Anacostia River • Rock Creek • Meet nutrient discharge limits of Chesapeake Bay Program • Schedule: 2005-2025 • Implemented under a Federal Consent Decree among: • United States Environmental Protection Agency (US EPA) • United States Department of Justice (US DOJ) • District of Columbia • DC Water 2

  3. Background Recent Bloomingdale Flooding 4 storms caused major flooding: July 10, 18, 19 and Sept 2, 2012 Mayor formed Task Force in Aug 2012 Task Force report delivered end of Dec 2012 Over 25 Recommendations: Regulatory Code Changes Operations & Maintenance • Engineering Measures • McMillan Stormwater Storage • First Street Tunnel • NEBT Public Outreach

  4. N Background Irving St. • NEB Protection Project 1 Michigan Ave. 1 North Cap. St. 2 First St. 2 Channing St. 3 3 Rhode Island Ave.

  5. First Street Tunnel • Overview N

  6. First Street Tunnel • Utility Relocations and Alley Closures

  7. First Street Tunnel • Channing Street Construction Staging Area

  8. First Street Tunnel • Adams Street Construction Staging Area

  9. First Street Tunnel • V Street Construction Staging Area

  10. First Street Tunnel • Pumping Station Construction Staging Area

  11. First Street Tunnel • Alternative Parking Areas WS-APA (21 spaces) • Strategy for Alternative Parking Areas • Most-impacted residents fronting staging area get assigned space • Parking Tags distributed to area residents • Security service at alternative parking areas to enforce permit/assigned parking • Shuttle for residents 24/7 BS-APA (77 spaces) 143 W-APA (16 spaces) M-APA (34 spaces, private, church and CM only) PS-APA (8 spaces, private, church only)

  12. Schedule • Construction: October 2013 – March 2016 • Mobilization in Neighborhood: February 2014 – July 2014 • APA’s Constructed: February 2014 – June 2014 • Channing Street Mining Shaft: October 2013 – March 2016 • Adams Street Diversions: June 2014 – March 2016 • First and V Street Diversions: April 2014 – March 2016 • Pumping Station: June 2014 – March 2016

  13. Public Meetings-FST Construction • Tuesday, January 7th • Focus on Channing Street/McMillan • Tuesday, January 14th • Focus on First & V Streets • Thursday, January 23rd • Focus on Flagler & Adams • Monday, January 27th • Focus on First & Thomas • All meetings are held at DC Water Bryant Street Pump Station at 301 Bryant Street NW • All meetings are held from 7-9PM

  14. Contact Information • First Street Tunnel Public Outreach • Tom Lindberg (202) 787.4738 • Email: Thomas.Lindberg@dcwater.com • DC Water Public Outreach • Emanuel Briggs (202) 787.2003 • Email: Emanuel.Briggs@dcwater.com