1 / 15

Generator Test Data, Generator Capability Curve, and NPRR 366 Terms

Generator Test Data, Generator Capability Curve, and NPRR 366 Terms. Mike Noth & Bracy Nesbit. March 14, 2012. Common Interests. Provide a stable and reliable system Comply with regulatory requirements (avoid non-compliance) Best value for customers. Review of Generator Capability.

chezarina
Télécharger la présentation

Generator Test Data, Generator Capability Curve, and NPRR 366 Terms

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Generator Test Data, Generator Capability Curve, and NPRR 366 Terms Mike Noth & Bracy Nesbit March 14, 2012

  2. Common Interests • Provide a stable and reliable system • Comply with regulatory requirements (avoid non-compliance) • Best value for customers

  3. Review of Generator Capability

  4. Area the Generator Can Safely Operate GENERATOR CAPABILITY

  5. Critical VSS Areas of Generator Operation Decreasing PF Increasing PF Increasing PF Decreasing PF

  6. NPRR 366 Problem • The system needs to adhere to a voltage profile to remain stable • No single generator can prop up or sink the system voltage

  7. Simple Nomograph of voltage from Generator Terminals to BES

  8. Actual Generator Test Data – At Generator Terminals The blue diamonds represent actual test points from leading and lagging reactive tests. Gen Gross are points measured at the Generator terminals. Red square represents 0.95 to 1.05 pu Voltage and +/- 0.95 power factor.

  9. Actual Generator Test Data – At POI The blue diamonds represent actual test points from leading and lagging reactive tests. Net to BES are points measured at the POI. Red square represents 0.95 to 1.05 pu Voltage and +/- 0.95 power factor. Dashed green lines roughly represent +/- 2% pu of Voltage profile value and bounded by red =/- 0.95 power factor lines.

  10. Existing Nodal Protocol 3.15 (3) Generation Resources required to provide VSS must be capable of producing a defined quantity of Reactive Power to maintain a Voltage Profileestablished by ERCOT. Generation Resources shall comply with the following Reactive Power Requirements: an over-excited (lagging) power factor capability of 0.95 or less and an under-excited (leading) power factor capability of 0.95 or less, both determined at the generating unit's maximum net power to be supplied to the ERCOT Transmission Grid and at the transmission system Voltage Profile established by ERCOT, and both measured at the POI. The Reactive Power requirements shall be available at all MW output levels and may be met through a combination of the Generation Resource’s Unit Reactive Limit (URL), which is the generating unit’s dynamic leading and lagging operating capability, and/or dynamic VAr capable devices. This Reactive Power profile is depicted graphically as a rectangle. …continued…

  11. Existing Nodal Protocol 3.15 (3) Generation Resources required to provide VSS must be capable of producing a defined quantity of Reactive Power to maintain a Voltage Profile established by ERCOT. Generation Resources shall comply with the following Reactive Power Requirements: an over-excited (lagging) power factor capability of 0.95 or less and an under-excited (leading)power factor capability of 0.95 or less, both determined at the generating unit's maximum net power to be supplied to the ERCOT Transmission Grid and at the transmission system Voltage Profile established by ERCOT, and both measured at the POI. The Reactive Power requirements shall be available at all MW output levels and may be met through a combination of the Generation Resource’s Unit Reactive Limit (URL), which is the generating unit’s dynamic leading and lagging operating capability, and/or dynamic VAr capable devices. This Reactive Power profile is depicted graphically as a rectangle. …continued…

  12. Present Protocol Requirement to meet the Voltage Profile Capacitive VAr devices have to be added There are no boundaries for the Generation Resource to supply reactive power in order to meet the Voltage Profile PF=0.95 or Less Decreasing PF Increasing PF Increasing PF PF=0.95 or Less Decreasing PF Reactive VAr devices have to be added

  13. Back to the NPRR 366 Problem • The system needs to adhere to a voltage profile to remain stable The Generation Resource must operate to the operating point determined by the Transmission Operator • No single generator can prop up or sink the system voltage The Generation Resource will operate up to the generator capability

  14. Generating Resource Operating Modes Required to Meet the Voltage Profile – Generator Operating Point determined by Transmission Operator VAR-002-1.1b R2. Unless exempted by the Transmission Operator, each Generator Operator shall maintain the generator voltage or Reactive Power output (within applicable Facility Ratings1) as directed by the Transmission Operator.

  15. Nodal Protocol 3.15 Option A Revision (3) Generation Resources required to provide VSS must be capable of producing a defined quantity of Reactive Power to maintain a Voltage Profile established by ERCOT. Generation Resources shall comply with the following Reactive Power Capability Requirements: an over-excited (lagging) power factor capability of 0.95 or less and an under-excited (leading) power factor capability of 0.95 or less, both determined at the generating unit's maximum net power to be supplied to the ERCOT Transmission Grid and at the transmission system Voltage Profile established by ERCOT, and both measured at the POI. The Reactive Power Capability requirements shall be available at all MW output levels and may be met through a combination of up to the Generation Resource’s Unit Reactive Limit (URL). , which is the generating unit’s dynamic leading and lagging operating capability, and/or dynamic VAr capable devices. This Reactive Power profile is depicted graphically as a rectangle. A Generating Resource may meet this requirement using VAr capable devices…continued…

More Related