CSCM

CSCM. Arjan Verweij, on behalf of the CSCM team. Technical info: CSCM mini review on 30/11/2011 ( indico 163905) CSCM session of the 3 rd splice review on 14/11/2012 ( indico 204695) MPE-TM of 13/6/2013 concerning results of the type test ( indico 257216)

chiku
Télécharger la présentation

CSCM

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. CSCM Arjan Verweij, on behalf of the CSCM team • Technical info: • CSCM mini review on 30/11/2011 (indico 163905) • CSCM session of the 3rd splice review on 14/11/2012 (indico 204695) • MPE-TM of 13/6/2013 concerning results of the type test (indico 257216) • and in many other meetings (CSCM, MPE-TM, TE-TM) Arjan Verweij, LMC meeting, 11/6/2014

  2. Outline • Motivation • Preparation phase and test phase • Detection and protection • Risks during the test • Program and planning • Conclusion Arjan Verweij, LMC meeting, 11/6/2014

  3. Motivation: Protection of the RB circuit • Normal operation: the current flows through the SC cable (magnet coil & centre of the bus). • Protection of the SC consists of: • QPS, detecting the quench  switching off the PC, opening the EE switches forcing the current to decay with t=100 s, • Bypass diodes, taking over the current if the coil quenches • Bus stabiliser, taking over the current if the bus quenches (either directly or due to heat propagating from a quenching magnet) Arjan Verweij, LMC meeting, 11/6/2014

  4. Motivation: Protection of the RB circuit The diode, the diode leads, and the bus stabiliser (referred to as RB bypass) should be able to carry the current during the decay without overheating. The RB bypass is a passive protection element, but is itself not protected and not redundant. The RB bypass has to be fully reliable, since nothing can reduce the decay time constant in the circuit (except massive quenching). Local overheating can result in burn-through, resulting in opening of the circuit & arcing, as experienced in 2008. Arjan Verweij, LMC meeting, 11/6/2014

  5. Motivation: Bus discontinuities Nr of circuits: 8 x RB, 8 x RQD, 8 x RQF In each RB circuit there are many discontinuities, each of which has a small possibility of having a local excess resistance. RB bus Diode bypass * Tested with limited accuracy, not ruling out possible critical defects In total there are about 28000 discontinuities in the 8 RB circuits!! Arjan Verweij, LMC meeting, 11/6/2014

  6. Motivation: expected quenches In the coming few years (until LS2) we will probably have: • O(10) dipole quenches if we stay at 6 TeV • O(100) dipole quenches if we go to 6.5 TeV • O(1000) dipole quenches if we push to 7 TeV Note that each quench will cause about 4 quenches in adjacent magnets (at 3-8 kA) and will cause about 100 m of busbar to quench. So a significant percentage (5%, 20%, 80%) of the RB bypass will see high currents. Testing is of course not needed if we are 100% sure that all connections are safe, also at high current. However, if we are not 100% sure, we better perform the CSCM to reduce known risks. Arjan Verweij, LMC meeting, 11/6/2014

  7. CSCM: preparation phase The CSCM is a test to fully qualify if the RB bypass can take over the current if the SC quenches. A kind of dry-run of the RB bypass. Basic idea • Connect the two 6 kA/200 V PC’s in series • Stabilize the entire sector at around 20 K, so the magnets and bus are not SC. Keep the DFB at 4.5 K. • Put a current pulse of maximum 11 kA, t=100 s Arjan Verweij, LMC meeting, 11/6/2014

  8. CSCM: test phase • Insert a few 100 A to open the diodes and stabilize the forward voltage. • Perform an ohmic measurement of all busbar segments • Quickly increase the current to Imax • Decay the current with t=88 s Example of a run with Imax=6 kA. Current and voltage on the converter. Current Voltage 3 4 1 2 Arjan Verweij, LMC meeting, 11/6/2014

  9. CSCM detection and protection • During normal operation the RB bypass is not protected, since nothing can change the decay time constant in the circuit (except massive quenching). • During the CSCM we use a “modified nQPS”, denoted as mQPS, to measure the voltage and protect the RB bypass. Arjan Verweij, LMC meeting, 11/6/2014

  10. Result from type test (before LS1) RB, 9 kA, Board A, Voltage RB, 9 kA, Board A, dV/dt We are able to clearly detect a defect in the bus starting a thermal runaway.

  11. CSCM risks • In case of QPS trigger, the converter is shut down and the current decays linearly to 0 A in about 0.2 s. • In the rare possibility of sudden opening of the circuit, the local heat dissipation in the arc will be less than 20 kJ, which is in theory sufficient to melt one cm of busbar, but cannot cause collateral damage. For example: creating a hole in the M-line requires more than 100 kJ. • We do not see any possibility for collateral damage. Arjan Verweij, TE-TM meeting, 10/6/2014

  12. CSCM program and planning • A thermal runaway in a defective part of the RB bypass depends on: • the MIIt’s • the instantaneous power, so the maximum current • during the current pulse. • Also the electromagnetic forces on the bus and diode leads depend on the maximum current. • We therefore plan to have a staged approach with increasing Imax: • 2 kA, 6 kA, 8 kA, 10 kA, 11 kA • with detailed analysis after each run. • The maximum current should be equal to the operation current • during Run 2, so up to 11 kA. Arjan Verweij, LMC meeting, 11/6/2014

  13. CSCM program and planning • Cool-down from 80 to 20 K. In the mean time (without impact on planning): • Change of the PC configuration from 12 kA/200 V to 6 kA/400 V • QPS commissioning • Temperature stabilization at 20 K: 1 week per sector. In the mean time: ELQA testing. • CSCM tests: 1 week per sector (incl. contingency) • Cool-down from 20 K to 1.9 K. In the mean time (without impact on planning): • Change of the PC back to the original configuration • Reconfiguration and locking of QPS in normal operation mode. • Powering tests of the HWC • EPC resources for 6 sectors are not identified yet. • The original planning had a 4 week period in 3 sectors reserved for the CSCM. For S67 we keep the planning. The other sectors can be done in 2 weeks (tbc after S67). Impact on global planning to be worked out by planning office. Arjan Verweij, LMC meeting, 11/6/2014

  14. Conclusions • The RB bypasses, including its 28000 discontinuities, should be fully reliable during LHC operation since they constitute the passive protection of the RB circuits, each having a stored energy of up to 1 GJ. • We can now perform the CSCM test in all sectors without swapping QPS boards, so with much less resources and risk than initially foreseen. • The CSCM type test last year was very successful!! • A test in one sector can be done in 2 weeks, including temperature stabilization. • There are no showstoppers - from Cryo, Powering, QPS, magnet, diode, and analysis point of view - to perform the CSCM. Proposal: • Perform a type test with final configuration in S67. • Prepare for CSCM test in the 7 remaining sectors. Arjan Verweij, LMC meeting, 11/6/2014