This update highlights the current status of campus improvements within the Loraine Independent School District as of January 21, 2012. Underground plumbing and electrical rough-in are complete across all areas. Concrete slabs have been poured in all prepared locations, while masonry work is 90% done in locker room areas and has commenced at the gymnasium. Steel erection is ongoing at the gymnasium, locker rooms, and JH/HS classroom areas. Looking ahead, masonry will continue, and we anticipate starting exterior drywall framing and sheathing soon.

cleo
Télécharger la présentation

Loraine Independent School District Construction Update - January 21, 2012

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Loraine Independent School District • Campus Improvements • Construction Update • January 21, 2012

  2. PROJECT STATUS

  3. PLANS

  4. PLANS

  5. SCHEDULE

  6. SCHEDULE STATUS • Underground Plumbing And Electrical Rough-in Is Complete In All Areas • Concrete Slabs Have Been Poured In All Areas That Are Ready At This Time. • Masonry is 90% Complete In Locker Room Areas And Has Begun At The Gymnasium. • Steel Erection Is In Progress at the Gymnasium, Locker Room And JH/HS Classroom Areas • Bus Barn Concrete Has Been Poured

  7. Masonry at Gymnasium

  8. Gymnasium Steel Structure

  9. Masonry and Steel at Gym

  10. Steel at JH/HS Classroom Wing

  11. LOOKING AHEAD • Masonry Will Continue Over The Next Month • Steel Erection Will Continue In All Areas • Exterior Drywall Framing And Sheathing Will Begin • MEP Wall And Ceiling Rough-In Will Follow CMU And Drywall Framing • The Bus Barn Structure Will Deliver By Mid February