1 / 10

LCLS SAFETY

LCLS SAFETY. Richard Hislop Construction Safety Coordinator. LCLS Safety Management. “LCLS Directorate ISEMS Plan” defines the roles and responsibilities of the Project Management Team (PMT) and holds the PMT responsible for the safe execution of the project.

cmooney
Télécharger la présentation

LCLS SAFETY

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LCLS SAFETY Richard Hislop Construction Safety Coordinator

  2. LCLS Safety Management • “LCLS Directorate ISEMS Plan” defines the roles and responsibilities of the Project Management Team (PMT) and holds the PMT responsible for the safe execution of the project. • “LCLS ES&H Plan” defines the standards and requirements for safe construction. • All project work is to be based on the process of job hazards analysis and documented work authorizations. No work is so important on this project that it need be done without due consideration for safety.

  3. Contracted work at Sector 20 and the Magnet Measurement Facility was completed 6/06. SLAC deconstruction of FFTB and assorted buildings was completed 8/27/06. Turner site work commenced 8/28/06. Tunneling operations will start 10/06. Construction Activities 46K contractor hours without injuries

  4. FFTB SLAB REMOVAL Surprise Configuration FFTB Demolition Removal in Progress BrokenWindshield Value of PPE

  5. PROJECT INJURY EXPERIENCE TO DATE Lost Time Injury Rate • SubContractors • 46 K Hours worked (08/28/2006) • Zero Injuries • LCLS Collaboration • 626 K Hours worked (08/28/2006) • Shoulder & back strain • 96 Days Worked Without Injuries (05/11/2006) Note: Injury rates based on 200 K hours (100 man years) of effort.

  6. Technical System Installations

  7. OUTREACH Management Safety Walks Lab-wide Communications

  8. DOE Stanford Site Office Inspection Report LCLS Safe Performance Observations

  9. WORK IN PROGRESS • Emergency / Crisis Management Coordination • Tunnel Rescue Training • Safe Performance Observations • Injector Safety Assessment Document • Fire Hazards Analysis

  10. Thank You

More Related