An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. DePaul University Project Management I - Work Breakdown Structure Instructor: David A. Lash

  2. PM Should Be Defined Process • Charter • Purpose • review and publish • SOW • A. Document goals, scope deliverables HL budget estimate • Review with Project board • Communication Plan • Document communication methods of various level • Review with project board, various stakeholders • Risk Strategy - A plan for managing risk & uncertainty • WBS - A tool for breaking down project into its component parts. • Project Plan • Execute HL Plan LL Plan

  3. OVERALL PLANNING STEPS

  4. What Is A WBS? • A tool for breaking down a project into its component parts. • Identifies all tasks in a project • Can be specified as chart form (figure 6.2) or outline form (figure 6.3) • It helps to: • Provide a detailed illustration of project scope - (doing WBS really helps understand scope of project) • Can help measure progress since, defines tasks in measurable units of work (defines work packages for workers.) • provides basis for team role definition • provides basis for cost estimates that includes equipment, labor, materials listed for each task

  5. What Is A WBS? • Summary Tasks - includes several subordinate tasks. • Work Package - each separate tasks. Work Packages Summary Tasks

  6. 3 Steps to WBS Development 1. Begin at The Top 2. Name all tasks needed to produce deliverables 3. Organizing the WBS (there are multiple ways to organize WBS.)

  7. Step 1 - Begin at The Top • List the major deliverables or high-level tasks from the scope • might also include intermediate deliverables (if major and not an end-product) Landscape Project Design Lawn Fence Grass Shrubs

  8. Step 2. Name all tasks needed to produce deliverables • For example put in grass might include • buy dirt & seed • spread dirt • spread seed • water for 2 weeks • Don’t worry about order of activities yet. • May need people closer to project tasks to help. • Can be difficult in new situations • for example, if never before executed a process or new technology use • May need to call team together to develop strategies for WBS development (high level)

  9. Step 3 - Organizing the WBS There are multiple ways to organize WBS. (See example 6.5) Some things to consider • organize in a way closer to • development process • organize in a way easier to manage • organize in way meaningful to sponsors.

  10. Some criteria for successful WBS 1. WBS broken down starting from top • Top down decomposition w/ each task lower a subset of above • Can use standard project management software • Make sure summary levels are meaningful

  11. Some criteria for successful WBS 2. Work packages must add up to summary tasks • subordinate tasks should add up to summary task • Take care not to omit needed tasks 3. Each summary task must be named as an activity that produces a product • That is, no open ended task - • e.g., perform research - could go on for ever. • Better to name the products of the research (e.g., research new smelting technique to develop harder swords.) • No leaky or open ended tasks • bad: database - what does it mean? • Better: test the DB - Much clearer • For example 6.4 shows major deliverables of design, lawn and fence

  12. More Criteria For Successful WBS 4. Provide an initial task description and exit criteria - When possible providing detail is very useful. It helps clarify task and gives a more uniform basis for review. - For example, Dig Trenches - dig approximately 45 trenches for fence about 20x12 inches deep. Implement Feature X - write and unit test feature X based on design. Review test results. 5. Formally Review WBS - Review the WBS with team members.

  13. Sizing Work Packages Correctly • Keep work packages between 1-10 days long. • Too long and becomes its own project • Too small may be part of another task • Keep work packages short enough so not to span status meetings • If break a task down into sub-tasks usually 1 of 3 reasons to do so: • It is easier to estimate (perhaps less uncertainty) • Is is easier to assign - (Keep single people or areas accountable) • It is easier to track • If not one of these 3 reasons, consider not further breaking down task.

  14. Other Sizing Guidelines • 8/80 Rule - No task should be smaller than 8 hours of labor or greater than 80 as a guideline. • Reporting Period Rule - Try to keep tasks shorter than the regular status meetings. (For example if weekly meetings, about 1 week long) • This can be difficult to achieve but if done so would be useful. • If its “useful” rule - breaking down tasks should make the management of project easier to estimate, assign or track.

  15. More on Work Package Sizing • Keeping units small can help control the project. • Consider examples in book • Waste treatment plant had project budge > 500 Million • contractors required to report work packages no larger than 2 weeks or 50K • This made identification of problems and cost overruns quicker to find • Microsoft has huge projects but require developers to analyze details in 1/2 day to 3 day chunks • people personally commit to their schedules • Can help to greatly increase estimations

  16. Building In Quality • Building quality into project can have a huge effect on its success • The later you find a problem the most expensive it is to fix. • Consider automobile manufacturing • Finding error in requirements VS development VS when the car is in the field • Need to ensure proper standards are set to judge the quality of the work.

  17. WBS Summary • WBS • breaks projects into parts • WBS Provides the structure for the project • Discussed 3 steps to develop WBS • Begin at top • Name all the tasks needed to produce deliverables • Organizing the WBS • Discussed work package size