The Wind Operations Task Force (WOTF) recommends that the Reliability Operating Standard (ROS) endorses the solution of conducting multiple CSC limit studies. ERCOT will enhance the frequency of calculating CSC limits to an hourly basis without needing any protocol changes. Currently, three out of five CSC studies (NtoS, StoN, NtoH) are completed, with two remaining. This initiative began on May 27 and requires posting outage and overload contingency pairs to ensure compliance with PRR 764.
E N D
Wind Operations Task Force recommendation for ROS vote, 12 June 2008 Issue 3f: “Run multiple CSC limit studies” • WOTF recommends ROS endorsement of solution. • ERCOT will increase the frequency of calculating CSC limits to hourly, with no Protocol change necessary. • Three out of five CSCs completed (NtoS, StoN, NtoH), two to go. • Started on May 27. • Posting of outage & overload contingency pairs will need to be added to verify compliance with PRR 764.