1 / 11

Background on RUC Process and Non-Spin Deployment Procedure

Background on RUC Process and Non-Spin Deployment Procedure. John Dumas Director Wholesale Market Operations. Outline of Presentation. Review RUC process Review RUC data for 7-13 and 7-18 Review Non-Spin Deployment Criteria. General Info on RUC Process.

cvelasquez
Télécharger la présentation

Background on RUC Process and Non-Spin Deployment Procedure

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Background on RUC Process and Non-Spin Deployment Procedure John Dumas Director Wholesale Market Operations Reliability Deployments Task Force Meeting

  2. Outline of Presentation • Review RUC process • Review RUC data for 7-13 and 7-18 • Review Non-Spin Deployment Criteria

  3. General Info on RUC Process • RUC Process recommends commitments or de-commitments of Generation Resources to ensure that there is enough Resource and Ancillary Service capacity, committed in the right locations, to reliably serve the forecasted Load on the ERCOT system. • Ramp Rates not considered. • Operator makes final decision. • Commitments are not made until necessary. Example: At 10 am RUC software suggests we need unit X for hour 16 and 17. Start up time is 1 hour. Operator does not commit at 10 am.

  4. Inputs to RUC • COP info on availability and HSL of Resources • Three Part Supply Offers (Only start-up and min energy used) • Resource Limits [minimum online time, minimum downtime ….] • Short Term Wind Forecast (COP HSLs reflect WGRPP values) • Load Forecast (reduced by bias shown on following slide) {1259 MW}

  5. How Resources are selected: • In evaluating a Resource for commitment, RUC considers: • Startup Offer (Warmth state taken into consideration) • Minimum Energy Offer • The Energy Offer curve is not used by RUC to select Resources

  6. Shown in COP as available, but there is no three part offer • To create a Three-Part Supply Offer, ERCOT will either: • Use 150% of any approved verifiable Startup and Minimum-Energy Offer costs. • Or, if that isn’t available • Use 150% of the Applicable Resource Generic Startup and Minimum-Energy Offer costs.

  7. Review of Bias subtracted from Load forecast

  8. Review of RUC Commitment Instructions May-July

  9. RUC Data for 7-13 (1 Resource) and 7-18 (14 Resources)

  10. Non-Spin Deployment Criteria • If SHDL – GTBD <= 200 AND Avail_Cap30Min < 500 MW – deploy ALL Non-Spin. (Full deployment of Non-Spin) • If SHDL – GTBD <= 200 AND Avail_Cap30Min < 1000 MW – deploy HALF of Non-Spin. (Partial deployment of Non-Spin) • If Physical Responsive Capability (PRC) < 2500 MW – deploy enough to recover PRC to 2500 (Partial deployment of Non-Spin) • If Physical Responsive Capability (PRC) < 2300 MW – deploy ALL Non-Spin. (Full deployment of Non-Spin) Avail_Cap30Min = SHASL – GTBD – 30MinLoadRamp 30MinLoadRamp=( NextHourLoadForecast – CurrentHourLoadForecast)/2 Physical Responsive capability = S (Min ( Max ( (HSL – TelemMW), 0.0), 0.2*HSL ) for online units + RRS from Load Resources

  11. Questions: Questions

More Related