An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Poplar Street Bridge City Arch River Consultant Presentation December 16, 2011 Room 160, St. Louis District Office

  2. MRB Phase 1

  3. MRB Phase 1

  4. PSB Interchange Scope Remove EB I-70 Ramp Remove and Replace PSB ramp to Memorial/WB I-70 ramp Remove and Replace SB I-55 Ramp with New Dual Lane Ramp Remove and Replace NB I-55 Ramp with New Dual Lane Ramp Convert I-70 Depressed Lanes from 4-Lane to 5-Lane Section Add Auxiliary Lane Between PSB and New I-70 Exit Ramp to Washington Avenue

  5. 2011 Improvements to PSB

  6. 2011 Proposed PSB Interchange Improvements

  7. 2011 Proposed PSB Interchange Improvements

  8. I-70 Typical Section in Depressed Area

  9. City Arch River 2015

  10. Land Bridge Over I-70

  11. City Arch River Land Bridge Scope Improvements to I-70, Memorial Drive, and City Streets Remove and Replace Walnut Street Bridge Remove Market, Chestnut, and Pine Street Bridges Construct Land Bridge over I-70 Between Market & Chestnut Remove NB Memorial Drive between Walnut and existing WB I-70 ramp Remove SB Memorial Drive between Chestnut and Market

  12. Land Bridge Over I-70

  13. City Arch River I-70 Ramps and 3rd Street /MLK Bridge Intersection Modifications Remove EB I-70 exit ramp to Memorial Drive and Replace with new EB I-70 entrance ramp from Washington Ave. Remove WB I-70 entrance ramp from Memorial Drive and Replace with a new WB I-70 exit ramp to Washington Ave. Geometric revision to the 3rd Street / MLK Bridge Intersection.

  14. I-70 Ramps to/from Washington Avenue

  15. 3rd Street / MLK Intersection Improvements

  16. Schedule for CAR Proposals Due - 1/13/12 Interview Selection- 1/20/12 Interviews- 2/1/12 Final Selection- 2/3/12 Negotiations Done- 3/2/12 Notice to Proceed- 3/9/12

  17. Schedule for PSB Proposals Due - 1/27/12 Interview Selection- 2/7/12 Interviews- 2/17/12 Final Selection- 2/21/12 Negotiations Done- 3/22/12 Notice to Proceed- 3/27/12

  18. Schedule for Ramps & MLK Proposals Due - 2/17/12 Interview Selection- 2/24/12 Interviews- 3/2/12 Final Selection- 3/5/12 Negotiations Done- 4/4/12 Notice to Proceed- 4/11/12

  19. AJR and NEPA Process Combined AJR for PSB / CAR Projects Separate NEPA documents AJR Submittal to FHWA by end of December NEPA for PSB Interchange requires Re-Evaluation of NMRB EIS NEPA for City Arch River requires EA Approved AJR and Signed NEPA Documents by May 2012 Some Risk in Moving Forward

  20. Contingencies • CAR – Funding from TIGER Grant • PSB- Approval on TIP • ALL 3 – Approval of NEPA and AJR

  21. Diversity

  22. DBE & Workforce PSB – 20% DBE CAR (Land Bridge) – 20% DBE Ramps & MLK – 20% DBE Monthly Workforce Plan

  23. Baseline Survey • Control Points to be provided by City Arch River to insure consistency on all projects.

  24. newriverbridge.org • http://www.newriverbridge.org/newsroom-library.html#plans