An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. OPPORTUNITY TO INVEST IN A FACTORY FOR PRODUCTION OF BOTTLED WATER ABD FRUIT JUICES “ELTA” El Tarik Oil d.o.o. Sarajevo

  2. Possibility for investing in the roduction of bottled water and fruit juices in BiH • There have been 33 producers of bottled water and fruit juices registered in BiH. • The BiH Market amounts to 235,000 tons of which import of goods amounts to 130.000 tons. The advantages of our products may be the following: • The production will be carried out at the most contemporary equipment, • Products of excellent physical and chemical characteristics will be produced. • The production process will be conducted in our plants by educated technologists and trained personnel in accordance with the EU standards. • Our brand products will be recognisable on the market. • Up-to-date designed wrapping material and labels.

  3. The activities conducted so far regarding this project • Purchase of land - 12 000 m². • Geology project has been drafted. • The borehole with the capacity of 8,4 l/swas constructed, which amounts to 50, 000 tons of work per one shift. (Image no.1) • The Study on Classification and Categorization of Mineral Water Reserves of “Sarajevsko vrelo-Ilidža” at the site of “Tukovi” – Plandište was drafted and then approved. The well in BiH was registered by the Federation Ministry of Energy, Mining and Industry and the procedure of the well registration by EU is still in progress. • Four analyses of water have been conducted by the Federation Institute for Public Health and one analysis was conducted by the German LaboratoryBerkefeld Celle, which confirm exelent quality of our water. • Feasibility study done. Image no.1: Drilling of well ‘Sarajevsko vrelo-Ilidža’

  4. Future investments • Drafting of building plan and construction of factory of 3150m². • Purchase of equipment and trial operation. Key factors to be taken into consideration regarding the mentioned investment • Existence of market • Excellent quality of our water as primary raw material. (Image no.2) Image no. 2: Water pumping from well ‘Sarajevsko vrelo-Ilidža’

  5. Financial construction of project • Estimated value of the project is 9, 7 million Euros • Own funds of 2, 7 million Euros have been invested. • Investments by prospective partners to the amount of 2, 3 million Euros. • It is planned to take loan for the construction of building and equipment to the amount of 4, 7 million Euros.

  6. Possible form of cooperation with prospective partner • We are seeking partner who is willing to invest 2,3 million Euros in this project, while our company, together with the prospective partner, would take a loan in the amount of 4,7 million Euros, whereby the required investment funds would be provided for the construction of the facilitates and purchase of equipment. • This idea is based on the fact that profit of 1 million Euros will be made on annual basis and the entire investment will be repaid in 7 years. • Own funds of 2, 7 million Euros have been invested.

  7. Basic company data • The current company has started to operate in 1996 and new activity has commenced in 2008. • Address: Ćamila Sijarića no. 26, Sarajevo, BIH; E-mail: eltariko@bih.net.ba; Tel:00 387 33 667-404; Fax:00 387 33 667-405. • Privately owned family business with 100% of ownership. • Director: Čengić Bakir. • The company owns: three gas stations, three tank cars; four apartments on Bjelašnica, the land of 12000 m2 (for the factory), the land of 3500 m2 (for new gas station). • Privately-owned family capital • Number of employees: 50 • New activity in production of bottled water and fruit juices may considerably rely on the existing organisation of the company dealing with turnover of oil derivates.