An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ISO Rules Update – 5.1.2 – Outage Cancellation 6.3.5 – Long Lead Time Energy 6.6 - Dispatch Compliance

  2. Rule 6.6 – Dispatch Compliance • Three complaints submitted to the AUC – hearing is currently scheduled to commence July 13, 2009 • Recommendation Paper issued October 30, 2008 • Recommendation Update issued January 15, 2009 • Draft rule posted March 5, 2009 • ************************************* • Comments due April 3, 2009 • Targeting to file with the AUC near the end of April, 2009

  3. Rule 6.6 – Dispatch Compliance • We are in consultation and comments are welcome and will be considered • Responses to the Recommendation Update will be posted this week • Do not intend to include the ramp profile form in the rules (see next slide) • Will issue a letter requesting participants to submit completed form before rule implementation • Default will be ETS submission

  4. Rule 6.6 – Dispatch Compliance Ramp Rate Submission Table

  5. 6.3.5 Long Lead Time Energy • Rules (6.3, 8 and appendix 7) filed with AUC in April 2008. • Objections filed with AUC in April 2008. • Hearing held in September 2008 • Decision 2009-007 issued in January 2009. • Pursuant to EUA subsection 20.5(1)(c) the AUC has directed the AESO to change the rule, e.g., • Update OPPs • Clarify circumstances • Define “incremental generation costs” • Provide a report mechanism

  6. 6.3.5 Long Lead Time Energy • Draft rules and OPPs posted March 5, 2009 • Comments due April 3, 2009 • Targeting filing of rules and OPPs with the AUC near the end of April, 2009 (no firm date set by AUC)

  7. Rule 5.1.2 – Generator Outage Coordination • Rules (5.1.2, 8 and appendix 7) filed with AUC in April 2008. • Objections filed with AUC in April 2008. • Hearing held in August 2008 • Decision 2008-137 issued in December 2008. • Pursuant to EUA subsection 20.5(1)(c) the AUC has directed the AESO to change the rule, e.g., • Direct the cancellation when there is a high probability of a shortfall • Provide a specific time period • Set out mandatory steps • Provide incremental generation costs • Provide reporting

  8. Rule 5.1.2 – Generator Outage Coordination • Targeting: • Draft rules and OPPs posted by end of April 2009 • File rules and OPPs with the AUC in July, 2009 (no firm date set by AUC)