1 / 22

Developing a Project Plan

Chapter 6. Developing a Project Plan. Luck favors to a prepared mind….. Louis Pasteur. Developing a Project Plan. The biggest and important part of a project plan is establishing the project network. Project Network.

darcie
Télécharger la présentation

Developing a Project Plan

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Chapter 6 Developing a Project Plan Luck favors to a prepared mind….. Louis Pasteur

  2. Developing a Project Plan The biggest and important part of a project plan is establishing the project network

  3. Project Network • The project network is the tool for planning, scheduling and monitoring project progress. • The project network presents a graphic display of the flow and sequence of work through the project • Provides the basis for scheduling labor and equipment • Provides an estimate of the project’s duration • Provides a basis for budgeting cash flow • Highlights activities that are “critical” and should not be delayed • Help managers get and stay on plan

  4. Project Network • The project networks are developed from the WBS

  5. Project Network • The project networks are developed from the WBS

  6. Project Network • The project networks are developed from the WBS

  7. A B D C Project Network - Terminology • Activity: an element of theproject that requires time. • Merge activity: an activity that has two or more preceding activities on which it depends. • Parallel (concurrent) activities: Activities that can occur at the same time if desired.

  8. C A B Project Network - Terminology • Path: a sequence of connected, dependent activities. • Critical path: the longest path through the activity network that allows for the completion of all project-related activities; D

  9. B C A D Project Network - Terminology • Burst activity: an activity that has more than one activity immediately following it (more than one dependency arrow flowing from it)

  10. Basic Rules in Developing Project Networks • Networks typically flow from left to right. • An activity cannot begin until all of its preceding activities are complete. • Arrows indicate precedence and flow and can cross over each other. • Looping is not allowed.

  11. Basic Rules in Developing Project Networks

  12. Basic Rules in Developing Project Networks

  13. Project Networks – Prototype Example This project is about preparing initial project plan regarding with building a new business center

  14. Project Networks – Prototype ExamplePartial Network

  15. Project Networks – Prototype ExampleComplete Network

  16. Project Networks – Prototype Example This project is about preparing initial project plan regarding with building a new business center

  17. Project Networks – Prototype ExampleNetwork Computation Process • Forward Pass—Earliest Times • How soon can the activity start? (early start—ES) • How soon can the activity finish? (early finish—EF) • How soon can the project finish? (expected time-ET) • Backward Pass—Latest Times • How late can the activity start? (late start—LS) • How late can the activity finish? (late finish—LF) • Which activities represent the critical path? • How long can it be delayed? (slack or float—SL)

  18. Project Networks – Prototype Example

  19. Project Networks – Prototype Example

  20. Prototype Example- Forward Pass

  21. Prototype Example-Backward Pass

  22. Prototype Example-Slack (Float) • Total Slack • The amount of time an activity can be delayed without delaying the entire project

More Related