1 / 26

Enterprise information systems project implementation: A case study of ERP in Rolls-Royce

Enterprise information systems project implementation: A case study of ERP in Rolls-Royce. Case Study published in International journal of production economics (2004) Presented by Tim Moir Bus550 June 3, 2013. The rise of Enterprise Resource Planning systems.

Télécharger la présentation

Enterprise information systems project implementation: A case study of ERP in Rolls-Royce

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Enterprise information systems project implementation: A case study of ERP in Rolls-Royce Case Study published in International journal of production economics (2004) Presented by Tim Moir Bus550 June 3, 2013

  2. The rise of Enterprise Resource Planning systems • The global economy requires internationalization of operations • Requires flexibility • Decentralized operations • Managing globally

  3. What does ERP do? • Increase the efficiency of an organization • Integrates separate functions such as manufacturing, finance, procurement, distribution into one system • Allows standardization of information across the entire enterprise, Information only entered once • Key Benefits • Business process automation • Timey access to management information • Improvement in the supply chain via the use of E-communication and E-Commerce

  4. Implementation • The biggest risk associated with a ERP is the implementation • Must be managed as an organizational change rather then a software installation • The way a company operates must be changed to make the implementation successful • Organizational resistance must be managed • ERP is very adaptable but not malleable • Bridge software to legacy systems

  5. Rolls-Royce Pre-ERP • New acquisitions lead to dramatic increase in size • Global company • Facilities in 14 countries by 1995 • New organizational structure in 1998 to better meet customer needs • 1500 systems, mostly internally developed • Expensive to create, difficult to manage • Data not accurate, consistent or accessible • In 1996 IT was outsourced to EDS

  6. Rolls-Royce Implementation Project • EDS provided the management team of specialists • Key – SAP Consultants • Project team is broken down into smaller segments • Each Operational Business Unit (OBU) has own planning team • Responsible for implementing working changes and training • Problems: • Cultural • Business • Technical

  7. Cultural Problems • Need to ensure high acceptance across all areas of the company • Illustrate improvements made by the company as a whole • Training split into two separate groups • SAP specialists conducted technical training • SAP specialist trained expect users • Other end-users were trained internally with EDS consultants • Training used demonstrations within the workplace, info meetings, and presentations for all 10,000 employees

  8. Business Problems • In order to ensure ERP works successfully, the business practices must fit the system • The internal business process had to be redesigned • Consisted of four steps • (1) Mapping the current process • (2) Identify issues / problems in the mapping • (3) Compare the mapping and problems with ERP process to identify issues in the new system • (4) Re-mapping to bring process inline with ERP • Why not make changes to ERP system?

  9. Technical Problems • Key issue has been the accuracy of data • Data from Legacy systems needed to be upload • Data duplication major concern • Systematic process of taking old systems offline • Customer user interfaces created to bridge data • Nine principal business processes

  10. Business Process Model

  11. Release Strategy • Implementation team had to define a release strategy for the entire project • Items to consider: • Third party software to be accredited by SAP • Business reports had to be justified and developed • Data had to be identified, validated, cleaned, loaded, and archived • Additional Hardware needed (1000 new PC’s, 6000 licenses, servers)

  12. Release Strategy

  13. Phase 1 – Strategy and Direction • Intense Study during Q1 of 1998 • Determine scope of project • Outline Plan • Determine Cost • Steering Committee for financial guidance • ERP Core Team was formed to oversee implementation process

  14. Phase 2 Planning Analysis & Convergence / Early Development • Created a detailed plan • Protégé system installed • Series of “High Level Process” workshops to discuss various business processes (involved 200 employees) • Another set of workshops “Business Simulation” (involved 300 employees)to forge relationship with ERP core team • Next steps included: • Preliminary design review • High level review • Critical design review • Implementation realization • Technical/Operation review • Post implementation review

  15. Project Changes • Significant timing change made during Phase 2 – The implementation phases (Wave 1 and Wave 2 were deferred for six months) • Changes due to: • Allow more time to prepare, train, and clean up data • Allow 5 additional months for pilot running and early development • Allow additional time for completion of projects needed for which ERP is dependent • Resolve difficulties with ERP at RR Allison division

  16. Phase 3 Implementation • The implementation phase was to large to be carried out at once • Broken into Wave 1 and Wave 2 • Wave 1 involved replacing the legacy systems currently in place with new systems • End of Wave 1 involved a pilot project at one RR facility • Successful Pilot project allowed full Go-Live company-wide one year later

  17. Phase 3 Implementation • Wave 2 lasted about one year in length • Not started until completion of Wave 1 • Concerned engine assembly, spares, logistics and human resources • Legacy were “read-only” • Once the ERP showed to work properly, old systems phased out • Changes during Implementation phases involved legacy systems. • Changes planned in a number of suites

  18. Suites 1, 2, 3 • In order to handle the adaption of the ERP from the “legacy systems” a three step process • Suite 1 • Plan the supply chain • Master schedule key program • Suite 2 • Plan and schedule the factory • Schedule the shop • Plan 3 • Operate the factory

  19. ERP Pilot • 3 months • Facility known a “number 4 shop” selected • Only produced 280 parts • Low numbers involved • Used as a test of the ERP system to demonstrate: • Business principles • Processes • Procedures • Role definitions and behaviors (including new roles) • Software, hardware, data transfers • Additional pilots

  20. Pilot projects • System testing and user acceptance • Creating ownership of process • Testing, Testing and more Testing • Data verification • Typical going live issues: • User authorization • Processing delays • Data variances • System processing

  21. Go-Live • Transferring legacy data • Stable environment for 10 weeks • Changes in data need to add to new system • Data can not be carried over and must start fresh • Old systems shifted to read-only • Constant monitoring of system to ensure proper operations

  22. System overview

  23. Project risks • Possible failure to align goals within organization • IT Hardware issues before or during implementation • Failure to provide adequate support • Resistance of change • Change not properly understood • Incomplete training • Data load issues • Project not given adequate priority • Maintenance issues • Financial data issues

  24. Questions What conditions let to the rise of the ERP? • Global marketplace • Decentralized operations • Business flexibility • All of the above What is the biggest risk associated with ERP? • Costs • Implementation • Strategy • None of the above

  25. Final Question Which of the following was not identified as a key problem • Cultural • Business • Procedural • Technical

  26. Thank you

More Related