1 / 6

January 2011 Closing Report -TGmb

January 2011 Closing Report -TGmb. Authors:. Date: 2011-01-20. Abstract. This document contains the TGmb closing report for January 2011. Accomplishments. Completed Initial SB Comment Resolution 454 comments First Recirculation SB to start early February

dawn-price
Télécharger la présentation

January 2011 Closing Report -TGmb

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. January 2011 Closing Report -TGmb Authors: Date: 2011-01-20 Dorothy Stanley (Aruba Networks)

  2. Abstract This document contains the TGmb closing report for January 2011. Dorothy Stanley (Aruba Networks)

  3. Accomplishments Completed Initial SB Comment Resolution 454 comments First Recirculation SB to start early February Scheduled Teleconference calls on February 25, 2011 10am Eastern (7am Pacific) 1-719-457-6209, Code: 712-821-8641 Timeline Analysis 11mb will incorporate 11s; planned 11mb ratification moves from Dec 2011 to March 2012 Slide 3 Dorothy Stanley (Aruba Networks)

  4. Current TGmb Plan of Record May 2008 – Issue Call for Comment/Input July 2008 – begin process input and old Interpretation requests Acknowledge previous Task Group referrals Sept 2008 – PAR revision process started Nov 2008 – close receipt of new input Nov 2008 – WG/EC approval of PAR Revision Dec 2008 – NesCom/SASB approval PAR Revision May 2009 – First WG Letter ballot Nov 2009 – Recirc start July 2010 – Conditional Sponsor Ballot Approval from EC August 2010 – Form Sponsor Pool (45 days) – Closes Sept 14 November 2010 – Initial Sponsor Ballot completion Jan 2011 – Sponsor Recirc. Start Nov 2011 – WG/EC Final Approval March 2012 – RevCom/SASB Approval Slide 4 Dorothy Stanley (Aruba Networks)

  5. Goals for March Recirculation Sponsor Ballot comment resolution (D7.0) Slide 5 Dorothy Stanley (Aruba Networks)

  6. References Dorothy Stanley (Aruba Networks)

More Related