Permit Process

Permit Process. Permitting Actions Sequence. 1. Levee District is the Permitting Authority 2. Applicant requests permit from local levee district (letter). 3. Joint site visit w/Levee District, Corps & applicant if necessary.

denali
Télécharger la présentation

Permit Process

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. PermitProcess

  2. Permitting Actions Sequence • 1. Levee District is the Permitting Authority • 2. Applicant requests permit from local levee district (letter). • 3. Joint site visit w/Levee District, Corps & applicant if necessary. • 4. Corps provides response and recommendation to Levee District (letter). • 5. Levee District approves or denies request. Copy furnished Corps.

  3. Permit Information Required • 1. Description of proposed work • Discuss proposed activities near levee • excavation, utility crossing, ramp, etc. • Crossing levee or parallel levee • 2. Site Map • Quad map showing the location of the proposed • Coordinates of work (GPS or Lat. Long.) • Section, Township, Range • 3. Plan Sheet • Plan view of proposed work with dimensions from levee • 4. Profile Sheet • Cross section view of work with dimensions from levee.

  4. Some levee districts use permit application forms.

  5. Common Permit Actions onRed River Levees • Ramp Construction • Utility Crossing • Electric Powerline Crossing • Pipeline construction, up-and-over & directional drilling • Excavation adjacent to levees

  6. Ramp Crossing Levee

  7. Utility Crossing Levee

  8. Pipeline Crossing Levee

  9. Excavation Near Levee

  10. Power Pole InstallationRequirements MININUM VERTICAL CLEARANCE VOLTS CLEARANCE 0-750 18 FEET 750 -15,000 20 FEET 15,000 – 50,000 22 FEET LANDSIDE RIVERSIDE POWERPOLE POWERPOLE LEVEE 40’ 40’

  11. Directional Drill under Leveewithout Supporting Soil Borings 300’ minimum distance at maximum depth R/S L/S Red River Levee 25’ minimum depth Below river bed Directional Drill path

  12. Directional Drill Supported with Soil Borings 300’ minimum distance for penetrating pervious sands R/S L/S Red River Levee 25’ minimum depth Below river bed Pervious Sands Directional drill path

  13. Directional Drill Exit on Riverside of Levee 50 Year Bank Migration Line Levee R/S L/S Min. 10’ Red River Directional Drill Path Exit point and pipeline to be minimum 10 ft. from levee stability control line at all times.

  14. Utility Crossing Detail

  15. Ramp Crossing Detail

  16. Ramp Crossing Detail

  17. Borrow Pit Detail