LeBreton Flats Infrastructure and Remediation Program: Planned Construction Activities Overview

This document outlines the planned construction activities for the LeBreton Flats Infrastructure and Remediation Program from February 2003 to July 2006. It details various construction phases including the Albert Booth Transitway, ORP Detours, fleet staging areas, and effective timelines for each activity. The program aims to enhance the local infrastructure while ensuring proper remediation during construction, thereby contributing to the successful redevelopment of the LeBreton Flats area.

denis
Télécharger la présentation

LeBreton Flats Infrastructure and Remediation Program: Planned Construction Activities Overview

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LeBreton Flats Infrastructure and Remediation Program Planned Construction Activities Revision 3.1 February 6, 2003

  2. S T U R Q P O N I M L J K February 2003 V CWM Construction Albert Booth Transitway

  3. S U R Q P O N I M L J K May 2003 V CWM Construction T Albert Booth Transitway

  4. S U R Q P O N I M L J K June 2003 V CWM Construction T Albert Booth Transitway

  5. S T U R Q P O N I M L J K July 2003 V CWM Construction ORP Detour ORP Detour Albert Booth Transitway

  6. S T U R Q P O N I M L J K August 2003 V CWM Construction ORP Detour Q also being remediated at this time ORP Detour Albert Booth Transitway

  7. S T U R Q P O N I M L J K September 2003 V CWM Construction ORP Detour Q also being used as a staging area at this time. ORP Detour Albert Booth Transitway

  8. S T U R Q P O N I M L J K October 2003 V CWM Construction ORP Detour Q also being used as a staging area at this time. ORP Detour Albert Booth Transitway

  9. S T U R Q P O N I M L J K November 2003 V CWM Construction ORP Detour ORP Detour Albert Booth Transitway

  10. S T U R Q P O N I M L J K December 2003 V CWM Construction ORP Detour ORP Detour Albert Booth Transitway

  11. S T U R Q P O N I M L J K January 2004 V CWM Construction ORP Detour Fleet ORP Detour Albert Booth Transitway

  12. S T U R Q P O N I M L J K May 2004 V CWM Construction ORP Detour Fleet CWM Staging Area & Commoms & Oregon Construction ORP Detour Albert Booth Transitway

  13. S T U R Q P O N I M L J K June 2004 V V CWM Construction ORP Detour Fleet CWM Staging Area & Commoms & Oregon Construction ORP Detour Albert Booth Transitway

  14. S T U R Q P O N I M L J K July 2004 V V CWM Construction ORP Detour Fleet CWM Staging Area & Commoms & Oregon Construction LeBreton Blvd. Albert Booth Transitway

  15. S T U R Q P O N I M L J K August 2004 V V CWM Construction Fleet CWM Staging Area & Commoms & Oregon Construction LeBreton Blvd. Albert Booth Transitway

  16. S T U R Q P O N I M L J K September 2004 V V CWM Construction Fleet CWM Staging Area & Commoms & Oregon Construction LeBreton Blvd. Albert Booth Transitway

  17. S T U R Q P O N I M L J K October 2004 V CWM Construction Fleet CWM Staging Area & Commoms & Oregon Construction LeBreton Blvd. Albert Booth Transitway

  18. S T U R Q P O N I M L J K November 2004 V CWM Construction Fleet LeBreton Blvd. Albert Booth Transitway

  19. S T U R Q P O N I M L J K December 2004 V CWM Construction Fleet Preston LeBreton Blvd. Albert Booth Transitway

  20. S T U R Q P O N I M L J K April 2005 V CWM Construction Oregon / Vimy Fleet Preston LeBreton Blvd. Albert Booth Transitway

  21. S T U R Q P O N I M L J K May 2005 V Oregon / Vimy Fleet Preston LeBreton Blvd. Albert Booth Transitway

  22. S T U R Q P O N I M L J K October 2005 V Oregon / Vimy Fleet Preston LeBreton Blvd. Albert Booth Transitway

  23. S T U R Q P O N I M L J K April 2006 V Oregon / Vimy Fleet Preston LeBreton Blvd. Albert Booth Transitway

  24. S T U R Q P O N I M L J K July 2006 V Oregon / Vimy Fleet Preston LeBreton Blvd. Albert Booth Transitway