1 / 30

GRS Bridge Abutments: Design Support and Instrumentation for Towlston Road Bridge at Rocky Run

GRS Bridge Abutments: Design Support and Instrumentation for Towlston Road Bridge at Rocky Run. Andy Kost, Karla Santacruz, George Filz, and Tommy Cousins Virginia Tech October 2011. GRS Bridge Abutments: Design Support and Instrumentation for Towlston Road Bridge at Rocky Run.

deron
Télécharger la présentation

GRS Bridge Abutments: Design Support and Instrumentation for Towlston Road Bridge at Rocky Run

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GRS Bridge Abutments:Design Support and Instrumentation for Towlston Road Bridge at Rocky Run Andy Kost, Karla Santacruz,George Filz, and Tommy Cousins Virginia Tech October 2011

  2. GRS Bridge Abutments:Design Support and Instrumentation for Towlston Road Bridge at Rocky Run • GRS Bridge Abutments • Towlston Road Bridge • Project Work Tasks • Schedule • Current Status

  3. GRS Bridge Abutments • Cross-section drawing • Photos from Huston Township, Pennsylvania

  4. Towlston Road Bridge • Before Washout • After Washout

  5. Project Tasks • Summarize the state of practice for GRS abutments • Develop GRS design requirements for Towlston Road Bridge • Design the instrumentation • Observe construction and install instrumentation • Test the bridge with a loaded truck • Prepare data reduction forms for long-term monitoring • Compare GRS abutment costs with alternatives • Develop conclusions and recommendations for GRS abutments • Develop recommendations for future research • Prepare a final report

  6. Schedule • Project start: Aug 2011 • Bridge Construction: Summer or Fall 2012 • Project completion: May 2013

  7. Current Status • Graduate Research Assistants • State of Practice Summary • Critical Review of Analysis and Design Procedure • GRS Short Course

  8. Graduate Research Assistants Andy Kost Karla Santacruz

  9. GRS Abutment State-of-Practice Summary • Review all relevant literature: 23 papers and reports.Status = complete • Prepare a short, readable summary for practicing engineers: • Technology description • Applications • Materials • Design • Construction • QC/QA • Maintenance Status = 50%

  10. Critical Review of Analysis and Design Procedure

  11. GRS Abutment Short Course • Taught by Daniel Alzamora,Geotechnical Engineer from FHWA Resource Center • Mike Adams, FHWA Turner Fairbanks will attend • November 9, 9:30 a.m. to 3:30 p.m. • VCTIR Auditorium, Charlottesville Meeting of project team immediately following short course.

  12. GRS Abutment Construction: Additional Photos

  13. Open to Traffic - 47 days

More Related