An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. INSY 3021 Time Study Auburn UniversitySpring 2005

  2. Establishment of Time Standards • Estimates • Historical records • Standards

  3. Estimates • Original method • Unfair due to variability among estimators • Looking at a job and judging the amount of the time needed

  4. Historical Records • Based on the record of previously performed similar jobs • Measures time over entire job, with no consideration of delays • Better than estimates (or lack of a standard)

  5. Time Study • Develops a time standard for performing a task • Measures work content, allows for fatigue, personal and unavoidable delays • Increases the efficiency of the equipment and personnel

  6. “A Fair Days Work” • The amount of work that can be produced by a qualified employee when working at a normal pace and effectively utilizing their time where work is not restricted by process limitations

  7. Responsibility • Notification • Proper lubricants, materials, feeds & speeds, knowledge of procedure • Normal pace, no introduction of new movements • Union support

  8. Equipment • Stopwatch • Decimal minute watch – 100 divisions (.01 minute) • Provides continuousorsnapback timing • Electronic watch – accuracy of .001 second (600 times more accurate) • Provides bothcontinuousand snapback timing

  9. Equipment (con’t) • Computer-Assisted electronic stopwatches • Video cameras • Time study board • Time study forms (TP) • Training equipment

  10. Time Study Elements • Watch operator for several cycles • Break task down into fine elements • Look for natural breakpoints using both sight and sound • Record elements in proper sequence • Do not repeat identical elements descriptions, just reference the previous #

  11. Timing • Record only what is necessary to rebuild later (TP) • Snapback: Watch is reset after each breakpoint of an element • Continuous: Watch is allowed to run for the entire job being evaluated

  12. Snapback Method • No clerical time needed to subtract from the previous observations as in continuous (TP) • Read and record Observed Time (OT) directly • Short element times are difficult to time • Possible cycle time lost during the snapback (N/A to electronic watch)

  13. Continuous Method • Continuous: Watch is allowed to run for the entire job being evaluated • Presents a complete record for the entire observation period • All delays and foreign elements are recorded • Clerical work required

  14. Foreign Elements • Things that are external to the process that delay the work moving forward • Include: Supervisor interruptions, power losses, defective parts, leaving workstation, tool breakage, etc… • Occurring during an element, write A, B, C, etc…In the NT block (TP)

  15. Missed Breakpoints • Immediately mark an “M” in the W column • If operator omits an element, draw a dash (-) through the applicable space in the W column

  16. Number of Cycles to Record • Tabulated data (TP) • Statistical methods

  17. Ratings • Normalize the readings to the “average operator” • Can be for the entire element or individual cycles • NT=OT x R/100

  18. Allowances • Typically about 15% • Personal interruptions • Fatigue • Unavoidable delay • Standard Time (ST) = NT (1 + allowance)

  19. Study Calculations • Start time, Finish time, Elapsed time, Time elapsed before study (TEBS), Time elapsed after study (TEAS), Total check time, Effective time, Ineffective time, Unaccounted time, Recording error (should not exceed ~ 2%)

  20. Questions & Comments