1 / 7

Interoperability of Meter Data Collection and Management Systems

Interoperability of Meter Data Collection and Management Systems. John Trudell and Tonnie Drummond US Army Corps of Engineers Engineering and Support Center - Huntsville 16 Aug 2012. Advanced Meter Requirement.

dieter
Télécharger la présentation

Interoperability of Meter Data Collection and Management Systems

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Interoperability of Meter Data Collection and Management Systems John Trudell and Tonnie Drummond US Army Corps of Engineers Engineering and Support Center - Huntsville 16 Aug 2012

  2. Advanced Meter Requirement • Advanced metering mandated by Energy Policy Act of 2005 (EPAct 2005), the Energy Independence and Security Act of 2007 (EISA 2007), policies, and directives. • Deadlines to install advanced meters • Electric by 30 Sep 2012 (EPAct 2005) • Gas and Steam by 30 Sep 2016 (EISA 2007) • Meter buildings with est. $35K/yr utility cost and/or 29,000 sq ft, and reimbursable tenant facilities.

  3. End State • Establish the energy information infrastructure (installation energy footprint) that will enable/provide: • Management of smart buildings • Energy Managers who are energy smart and more effective to meet energy reduction goals. • Building occupants are energy aware and actively participate in energy reduction actions. • Reduce energy waste • Continuous improvements in energy efficiencies • Meet the requirements of NetZero by 2030.

  4. Define the scope of the action • What data do we need to collect and analyze? • What is the data flow architecture? • What hardware and software is needed to collect and transfer data? • What hardware and software is currently installed and needs to be integrated into the system? • How will the system security (Information Assurance) be tested, implemented, and maintained? • Who will sustain/maintain the systems?

  5. Installation Meter data collection Enterprise Meter Data Flow Meter Data Management 3) Transmit raw meter data Electric meter 1) Gas pulse counts 2) Collect raw meter data Gas Meter 4) Analyze meter data Gateway server Front End Server 1) Water pulse counts 5) Report Generation Energy manager views data via a web portal Security Accreditation Boundary Water Meter

  6. Three Challenges 1) Communication – Army-wide End State Data Flow Architecture • 2) Communication – System Documentation • DIACAP - System Hardware/Software • Life Cycle Management • 3) Communication – Meter System Install Coordination • Meter Install Team (Government and Contractor) • Installation – Building power outage • IA/IT Community

  7. Contact information John Trudell Program Manager – MDMS (256) 895-1322 (w) (256) 690-7196 (c) john.a.trudelliii@usace.army.mil Tonnie Drummond IA/IT Specialist IAM EEDRS (256) 895-1730 (w) (256) 690-1538 (c) tonnie.f.drummond@usace.army.mil US Army Corps of Engineers Engineering and Support Center 4820 University Square Huntsville, AL 35816-1822